04 - 043624 CONCRETE TRESTLE



FEBRUARY 4, 1999





PROJECT CONTACT PERSONS
PROJECT MANAGERHelena "Lenka" Culik-Caro(510) 286 - 5759
PUBLIC AFFAIRS OFFICEAnne Tobias(415) 989-1446 (EXT-12)
CONTRACTORWest Coast Bridge Inc.(707) 746-8028

CONTRACT INFORMATION
CONTRACTOR'S BID$7,483,819
NUMBER OF WORKING DAYS480
CONTRACT AWARDEDJuly 25, 1997

PROJECT SCOPE HIGHLIGHTS

The Trestle portion represents the majority of the Bridge, connecting the High Rise with the eastern shore of the Bay. The Trestle is 5.15 miles long, and consists of 877 thirty-foot spans. This portion carries two lanes in each direction, and for the majority of its length is only 10 feet above the Bay. The seismic retrofit of the Trestle will entail.




PROJECT PHOTOS

Seismic Retrofit of the Trestle Portion of San Mateo-Hayward Bridge
Contractor Support Barge