Caltrans Office Engineer

Viewing inquiries for 06-0P7004

Submit new inquiry for this project


Inquiry #1: For Bid Item # 11, is the State anticipating that there will only be 1 "must-grind", used as a lump sum to cover all possible "must-grinds", or furnish a price per "must-grind" as needed in the field?
Inquiry submitted 02/13/2013

Response #1:Submitted for consideration.
Response posted 02/13/2013


Response #2:Bid item #11 "Prepaving Grinding Day" is priced as per "each" day as needed in the field.
Response posted 02/21/2013




Inquiry #2: The typical cross sections on Sheet X-1 indicates that the paving outside the ETW varies from 0' to 2'. There are currently no paved shoulders on this section of Highway, only gravel and base.

As your quantitiy would indicate you plan to pave a 2' shoulder throughout the project, Is it Caltrans' intent to perform up to 2' of paving on the existing shoulders? If so, how will the preparation of these aggregate base shoulders be paid for (i.e. clearing, filling, grading)?

Inquiry submitted 02/21/2013

Response #1:Submitted for consideration.
Response posted 02/21/2013


Response #2:The proposed 0.1' HMA overlay is from existing Edge of Pavement(EP) to EP, regardless of the existing shoulder width.
Response posted 02/22/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.