Inquiry #1: Please provide the base CAD files for the plans and cross-sections, so bidders can reference CAD for quantity take-off.
Thank you,

Inquiry submitted 07/18/2012

Response #1:Submitted for consideration.
Response posted 07/18/2012


Response #2:Download cross-sections below.


Response posted 07/24/2012




Inquiry #2: Can you please provide PDF files of the project cross sections.
Inquiry submitted 07/31/2012

Response #1:I'll post your request, but in case you did not know, you can download a free Microstation viewer - http://www.bentley.com/en-US/Products/Bentley+View/
Response posted 08/01/2012


Response #2:Submitted for consideration.
Response posted 08/01/2012


Response #3:Download the pdf cross sections below:


Response posted 08/02/2012




Inquiry #3: Below four Caltrans Projects on Route 580 from Greenville Rd to Foothill Blvd are potentially awarded to four different Contractors. But the construction phases of these four contracts may happens as same time. Therefore, its will create a lot of traffic control conflicts during lane closures for paving operation. Can Caltrans change the “A+B bid” to a regular Basis “A” bid only?

- #04-4A07U4 (Bid open on 04/25/2012)
- #04-2908E4 (Bid open on 08/29/2012)
- #04-2908V4 (Bid open on 09/05/2012)
- #04-2908C4 (Bid open on 09/19/2012)

Thanks,

Inquiry submitted 08/04/2012

Response #1:Submitted for construction.
Response posted 08/06/2012


Response #2:04-2908E4 and 04-2908V4 will remain Time+Cost.
Response posted 08/27/2012




Inquiry #4: Is the State providing Construction Land Survey services? Is so, is it for Prime or just Caltrans? Does Prime need to contract survey services?
Inquiry submitted 08/06/2012

Response #1:Submitted for consideration.
Response posted 08/07/2012


Response #2:The State will provide staking as needed upon request by prime contractor. State will provide survey in accordance with Chapter 12 of the survey manual.
Response posted 08/09/2012




Inquiry #5: Caltrans currently has three projects along the Highway 580 corridor out to bid:
04-2908C4, 04-2908V4, and 04-2908E4
Construction on these contracts will be concurrent with each other. Caltrans is bidding each of these under the A+B format. Due to the likelihood that the work on each these projects will impact the work on the adjacent projects, shouldn’t these project be bid under the standard (non-A+B) working day format?

Inquiry submitted 08/06/2012

Response #1:Submitted for consideration.
Response posted 08/07/2012


Response #2:See BI#3.
Response posted 08/27/2012




Inquiry #6: Where is the work for Bid Item 167 “Slope Paving”? Spec section 10-1.83 says it is for the slopes under the end of bridges but none is shown at the bridges. Retaining Wall 18 (plan sheet 667) shows what appears to be slope paving but there is no Qty given for it. It also looks as if this location would only account for about 50 cy.
Inquiry submitted 08/13/2012

Response #1:Submitted for consideration.
Response posted 08/14/2012


Response #2:Please bid per current contract documents.
Response posted 08/17/2012




Inquiry #7: There are two bid items for the chain link railing. One chain link railing (bid #183) is per detail B11-7. The modified chain link railing (bid item #184)does not have a detail.
Please provide a detail for the modified chain link railing.

Inquiry submitted 08/13/2012

Response #1:Submitted for consideration.
Response posted 08/14/2012


Response #2:No detail has been provided for the Chain Link Railing (Mod) shown on Sheet No. 631. Only the height has been reduced from 6'-1 1/2" to 3'. See the Stand Plans, Detail B11-7.
Response posted 08/16/2012




Inquiry #8: The project plans include a detail for cable railing (sheet 582). I do not see cable railing called out on any other plan sheets, nor do I see a bid item for cable railing.
Please clarify if there is cable railing to be installed on this project.
If so, please provide a location and quantity for cable railing.

Inquiry submitted 08/13/2012

Response #1:There is No Cable Railing work for this project.
Response posted 08/16/2012




Inquiry #9: Caltrans project in Petaluma 04-2640U4 ($66 Million)has been postponed to 09/05/2012 and now it is in conflict with this project 04-2908V4 ($30 Million). Please consider postponing 04-2908V4 to another date since it would difficult for contractors to bid both projects on the same day.
Inquiry submitted 08/14/2012

Response #1:Submitted for consideration.
Response posted 08/15/2012




Inquiry #10: With this bid being postponed to Friday, October 5th, will the bid opening still be at 2:00 p.m., or will it be moved to 10:00 a.m.?
Inquiry submitted 08/25/2012

Response #1:Submitted for consideration.
Response posted 08/27/2012


Response #2:October 5 is the bid opening for this project and it is for 10:00 am.
Response posted 08/28/2012




Inquiry #11: 1) On Sheet E-39 between “B LINE” station marks 631 and 632 there is a Fiber Optic conduit run that runs from the Fiber Optic Vault (F/O) to a #5 box that has no designation. (A) What size and type conduit is this run?
Inquiry submitted 09/10/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:On Sheet 484 E-39 there are no station marks 631 and 632. The station marks start at “B Line” 675 and end at 689. The size and Type of the Conduit its 2”C, MT as shown in the Detail A on same sheet.
Response posted 09/12/2012




Inquiry #12: On Sheet E-65 at approximate station mark 376 there is an existing conduit run that is marked 1A-29 and has an arrow pointing “in the distance” that does not show where the end point is. Note 29 directs us to “Remove All Existing Conduits”. (A) Please tell or show where this conduit run terminates so that the conduit removal work can be properly estimated.
Inquiry submitted 09/10/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:Submitted for consideration.
Response posted 09/10/2012


Response #3:This part of the work is also referenced on sheet E-3 at station 376, which then references sheet E-20. The work continues west to approximate Sta 372+50.
Response posted 09/12/2012


Response #4:The questioned conduit removal shown on E-65 is part of the permanent work, reference is made in the sheets E-3 and E-20. The total length of conduit removal is approximately 300’.
Response posted 09/17/2012




Inquiry #13: On Sheet E-65 we are directed to relocate pole light #017812. Next to the (RL) designation is a designation (1B). (A) What does the (1B) note refer to?
Inquiry submitted 09/10/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:The note should be "1A" not "1B."
Response posted 09/11/2012




Inquiry #14: The detail on sheet E-72 calls out ½” messenger wire. The details on sheets E-73 & E-74 call out a 3/8” messenger. (A) when is a ½” messenger wire required and when can a 3/8” messenger be used?
Inquiry submitted 09/10/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:Messenger wire on E-72 should be 3/8" not 1/2".
Response posted 09/17/2012




Inquiry #15: On sheets E-68 through E-71, some of the Temporary Wood Poles have a “B” designation attached to them. (A) What does the “B” designation refer to on these wood poles?
Inquiry submitted 09/10/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:The "B" designation is for "B Line " stationing.
Response posted 09/11/2012




Inquiry #16: On sheet E-71 we are directed to relocate pole light #012712 but no new location is given. (A) Please designate the new location for pole light #012712.
Inquiry submitted 09/10/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:The new location is shown on E-10, Sta "B" 637+93.
Response posted 09/18/2012




Inquiry #17: Will a copy of the "Sign In Sheet" from the mandatory pre-bid meeting be postyed for this contract?
Inquiry submitted 09/10/2012

Response #1:You can view the attendees at the web link below. See "Event E."

http://www.dot.ca.gov/dist4/smallbusiness/outreach_archive.htm
Response posted 09/10/2012




Inquiry #18: The X-sections that have been made available are missing details for the retaining walls. The scale also creates a problem interpreting slopes etc since the vertical 1" = 5' and the Horiz. 1" = 20'. Can Caltrans provide x-sections scaled similar to other projects?
Inquiry submitted 09/10/2012

Response #1:Submitted for consideration.
Response posted 09/10/2012


Response #2:The requested X-sections are not available.
Response posted 09/11/2012




Inquiry #19: Per Bidder Inquiry No. 10 the State in their response to the inquiry question stated bids will be open at 10 a.m. The initial time was 2 p.m. per the Contract Specifications and Addendum No. 1 only changed the date not the time. Please note as stated on your web page for inquires that " The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract". Therefore if the State intends to change the time please issue a formal addendum with the time change.
Inquiry submitted 09/11/2012

Response #1:Submitted for consideration.
Response posted 09/12/2012




Inquiry #20: On sheet E-86 beginning at station mark 677 there is a 4” conduit run with (2) #6 conductors (120 V TMS) that ends at N. Livermore Avenue. This conduit run appears to be mirrored on the Traffic Operation System plans with (3) 3/0, (4) 1/0 and (6) #6 conductors (total). (A) Is this the same conduit run?
Inquiry submitted 09/18/2012

Response #1:Submitted for consideration.
Response posted 09/18/2012


Response #2:Yes, this is the same conduit shown on E-39.
Response posted 09/19/2012




Inquiry #21: On sheet E-35 we are directed to join conduit to existing conduit (CC) between the new 3rd and 4th lane of the freeway for the new loop detectors. (A) Is it really the intention that we should plan on open cutting the freeway to intercept this conduit run?
Inquiry submitted 09/18/2012

Response #1:Submitted for consideration.
Response posted 09/18/2012


Response #2:At this location, EB lanes are widening to accommodate the additional lanes and retaining wall. Intention is only to replace the affected conduit not to open cut the freeway.
Response posted 09/19/2012




Inquiry #22: On Sheet S-10, there is a sign that gets relocated TO approximately “B” 616+00 from approximately “B” 632+00. On sheet E-89 there is a faint symbol showing an existing sign at “B” 616+00 but I do not find this sign listed on any other electrical plan. (A) Please detail where the electrical information for the sign relocated to “B” 616+00 is.
Inquiry submitted 09/18/2012

Response #1:Submitted for consideration.
Response posted 09/18/2012


Response #2:This is the relocation of the existing EMS sign. It is referring to the existing EMS sign on E-35, which should be relocated to Sta “B” 637+00 on E-36, NOT as shown on E-89 and S-10.
Response posted 09/20/2012




Inquiry #23: On sheet 444 of the plans Sound Wall Asthetics it shows the block pattern for the 12 ft. section on RW which is only 270 ft. of the 1973 foot wall. For the remainder of the wall which is only 9ft4in., does the 4 eliminated course come off of the bottom of the pattern? Also on the same sheet there are 3 areas in the repeating patterns that are outlined with Block A, on the left portion is calls for the block in the middle to be block B and on the right portion it calls for the same block to be Block D. What is the block in the middle portion to Be?
Inquiry submitted 09/25/2012

Response #1:Per Caltrans Standard Plan B15-6 the height of SW is 12'-4" because the Sound Wall on Concrete Barrier Type 736SV (Ht. of Barrier = 3 ft).



The height of Sound Wall block is 8 inch = 0.66 ft as shown on sheet 444 of the plans. Also please see the Caltrans Std. Plan B15-6 which shows he Sound Wall height considered for the design.



The Ht. of SW is break up in portion as follow:


    3' Ht. of Barrier + (0.66*#14 no. of block = 9'-4") = 12'-4" Ht of SW.


Block B on the Sheet 444 is pointed incorrectly. It should be pointed to the middle potion as shown in the attachment.

Response posted 09/26/2012




Inquiry #24: Per the description and quantities for Retaining Wall No. 16 (Sheet R-17), there is 47 LF of CL-4 to be installed. Sheets R17 & R18 do not show the CL-4 on top of retaining wall 16, nor is there an elevation showing how the CL-4 will be attached.

Please provide a detail showing how the CL-4 will be installed at Retaining Wall 16.

Inquiry submitted 09/26/2012

Response #1:Submitted for consideration.
Response posted 09/27/2012


Response #2:Chain Link Fence (Type CL-4) goes on top of Wing wall at Arroyo Seco RCB. Detail for the same is shown on the sheet 181 Drainage Details DD-15. Quantity for CL-4 is included along with the Retaining Wall No.16.
Response posted 09/28/2012




Inquiry #25: Please provide the "H" on sheet 172 for the Adjust DI to grade detail.
Inquiry submitted 09/26/2012

Response #1:Submitted for consideration.
Response posted 09/27/2012


Response #2:The "H" value varies from location to location. Per Note 3 under detail "Adj DI TO Grade" on Sheet 172 it says" Contractor to adjust "H" so that the Top of Grade is flush with finish grade of the road.
Response posted 10/02/2012




Inquiry #26: On sheet 608 on the Bridge Typical Section, there are two 2” conduits shown in the barrier. These conduits do not show on any of the electrical drawings. (A) What system and/or Bid Item do these conduits belong to? Are they empty conduits? If not, what is to be installed in these conduits?
Inquiry submitted 10/01/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:They are 2 fiber optic conduits. Download Plan Sheets E-1 & E-40 below.

E1 & E40
Response posted 10/03/2012




Inquiry #27: There is a WVDS pole shown on sheet E-42 to be removed and salvaged. (A) Does this pole have a “Repeater” or an “Access Point” mounted on it?
Inquiry submitted 10/01/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:This WVDS is an "Access Point."
Response posted 10/03/2012




Inquiry #28: There is a WVDS pole shown on sheet E-39 to be removed and salvaged. (A) Does this pole have a “Repeater” or an “Access Point” mounted on it?
Inquiry submitted 10/01/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:The WVDS pole has an "Access Point".
Response posted 10/03/2012




Inquiry #29: There is a WVDS pole shown on sheet E-34 to be removed and salvaged. (A) Does this pole have a “Repeater” or an “Access Point” mounted on it?
Inquiry submitted 10/01/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:The WVDS pole on E-34 has a "Repeater".
Response posted 10/03/2012




Inquiry #30: There is a WVDS pole shown on sheet E-22 to be removed and salvaged. (A) Does this pole have a “Repeater” or an “Access Point” mounted on it?
Inquiry submitted 10/01/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:The WVDS pole on E-22 has an "Access Point".
Response posted 10/03/2012




Inquiry #31: On sheet E-86 there are 10 loops (approx. 676+50) to be installed with a Note (1A) designation (Part of Permanent work installed under temporary phase). The permanent loops in this location are shown on sheet E-39. In this case, the loops shown on the temporary plan should remain as part of the permanent however, with the lane configuration change and the addition of a median shoulder, the new loops (and pull box) on sheet E-39 are no longer in the same position as the loops (and pull box) shown as (1A) permanent on the temporary plans. Therefore, it appears that the loops in this location will actually need to be installed both under the temporary work and the permanent work. (A) It is my belief that the work on sheet E-86 with a (1A) designation should actually be temporary work separate from the permanent work and not have a (1A) designation. Please confirm.
Inquiry submitted 10/02/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:New loops are required for both permanent and temporary work.
Response posted 10/05/2012




Inquiry #32: On sheet E-87 there are 10 loops (approx. 701+25) to be installed with a Note (1A) designation (Part of Permanent work installed under temporary phase). The permanent loops in this location are shown on sheet E-40. In this case, the loops shown on the temporary plan should remain as part of the permanent however, with the lane configuration change and the addition of a median shoulder, the new loops (and pull box) on sheet E-40 are no longer in the same position as the loops (and pull box) shown as (1A) permanent on the temporary plans. Therefore, it appears that the loops in this location will actually need to be installed both under the temporary work and the permanent work. (A) It is my belief that the work on sheet E-87 with a (1A) designation should actually be temporary work separate from the permanent work and not have a (1A) designation. Please confirm.
Inquiry submitted 10/02/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:New loops are required for both permanent and temporary work.
Response posted 10/05/2012




Inquiry #33: On sheet E-88 there are 10 loops (approx. 731+75) to be installed with a Note (1A) designation (Part of Permanent work installed under temporary phase). The permanent loops in this location are shown on sheet E-43. In this case, the loops shown on the temporary plan should remain as part of the permanent however, with the lane configuration change and the addition of a median shoulder, the new loops (and pull box) on sheet E-43 are no longer in the same position as the loops (and pull box) shown as (1A) permanent on the temporary plans. Therefore, it appears that the loops in this location will actually need to be installed both under the temporary work and the permanent work. (A) It is my belief that the work on sheet E-88 with a (1A) designation should actually be temporary work separate from the permanent work and not have a (1A) designation. Please confirm.
Inquiry submitted 10/02/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:New loops are required for both permanent and temporary work.
Response posted 10/05/2012




Inquiry #34: On sheet E-89 there are 10 loops (approx. 612+00) to be installed with a Note (1A) designation (Part of Permanent work installed under temporary phase). The permanent loops in this location are shown on sheet E-34. In this case, the loops shown on the temporary plan should remain as part of the permanent however, with the lane configuration change and the addition of a median shoulder, the new loops (and pull box) on sheet E-34 are no longer in the same position as the loops (and pull box) shown as (1A) permanent on the temporary plans. Therefore, it appears that the loops in this location will actually need to be installed both under the temporary work and the permanent work. (A) It is my belief that the work on sheet E-89 with a (1A) designation should actually be temporary work separate from the permanent work and not have a (1A) designation. Please confirm.
Inquiry submitted 10/02/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:New loops are required for both permanent and temporary work.
Response posted 10/05/2012




Inquiry #35: 5) On sheet E-90 there are 10 loops (approx. 631+80) to be installed with a Note (1A) designation (Part of Permanent work installed under temporary phase). The permanent loops in this location are shown on sheet E-35. In this case, the loops shown on the temporary plan should remain as part of the permanent however, with the lane configuration change and the addition of a median shoulder, the new loops (and pull box) on sheet E-35 are no longer in the same position as the loops (and pull box) shown as (1A) permanent on the temporary plans. Therefore, it appears that the loops in this location will actually need to be installed both under the temporary work and the permanent work. (A) It is my belief that the work on sheet E-90 with a (1A) designation should actually be temporary work separate from the permanent work and not have a (1A) designation. Please confirm.
Inquiry submitted 10/02/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:New loops are required for both permanent and temporary work.
Response posted 10/05/2012




Inquiry #36: When trenched conduits for temporary facilities follow the same alignment of permanent trenched conduits, can the temporary conduits be placed in the Permanent conduit trench?
Inquiry submitted 10/02/2012

Response #1:Submitted for consideration.
Response posted 10/02/2012


Response #2:The temporary conduit trench should not be interfered with the permanent conduit trench. So, no temporary conduit trench in permanent conduit trench.
Response posted 10/05/2012






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.