Viewing inquiries for 12-0L9704

Submit new inquiry for this project


Inquiry #1: Regarding Page 7 of the Special Provisions, Section 12-3.13 Impact Attenuator Vehicle. I don't understand the necessity, as the work is taking place on city streets, governed by signalized intersections. Are these actually required, and if so, why?

Thanks,
Stephen

Inquiry submitted 09/03/2013

Response #1:Submitted for consideration.
Response posted 09/03/2013


Response #2:Bid as you see it.
Response posted 09/05/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.