Inquiry #1: Revised Standard Specifications section 19 EARTHWORK, replaces section 19-4 ROCK EXCAVATION, indicating that the native material will require unconventional equipment and methods to remove the material down to finish grades; but there is not enough information to determine if hard rock will be encountered. Please advise if hard rock will be encountered within the cut areas on the job.
Inquiry submitted 05/05/2017

Response #1:No. Rock Excavation will not be required.
Response posted 05/08/2017




Inquiry #2: Please advise what makes BI 16 ROADWAY EXCAVATION (UNSUITABLE MATERIAL) to be classified as unsuitable.
Inquiry submitted 05/05/2017

Response #1:Per Section “1-1.07B Glossary” of the 2015 Standard Specifications, the following definition applies:
“Material encountered below the natural ground surface in embankment areas . . . that the Engineer determines to be . . . inappropriate for the planned use.”
The planned use is stable and correct drainage contours.

Response posted 05/08/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.