Viewing inquiries for 06-0T3204

Submit new inquiry for this project


Inquiry #1: Line items 89 through 93 detail warranty tape striping or markings. The new Caltrans warranty striping specification, issued July 11, 2017 allows other materials to be used. Please clarify the allowance of other materials.
Inquiry submitted 09/01/2017

Response #1:Submitted for consideration.
Response posted 09/05/2017


Response #2:
Use the warranty tape specified on the project plans and the specifications.
Response posted 09/25/2017




Inquiry #2: For the SAMI-R:

1. Missing Bid Item for Sand Cover, which is part of the Flush Coat. Please add Bid Item.

2. Bid Item Quantities are off, below are typical quantities for SAMI-R:

Asphalt Rubber Binder .55-.65 Gal/SY
Precoated Screenings 28-40 lbs/SY
Asphaltic Emulsion (Flush Coat) .05-.06 Gal/SY (Undiluted)
Sand Cover 2-6 lbs./SY

Please clarify.

Inquiry submitted 09/11/2017

Response #1:
Submitted for consideration.
Response posted 09/11/2017


Response #2:
Bid per current contract documents.
Response posted 09/22/2017




Inquiry #3: please verify if Item 50-Furnish Sign Structure (Tubular) is to be Galvanized & Painted, or just Galvanized, there was no mention in the special provisions about paint or a color number.
Inquiry submitted 09/20/2017

Response #1:
Submitted for consideration.
Response posted 09/20/2017


Response #2:
Refer to Addendum No. 1, dated September 22, 2017.

Response posted 09/22/2017




Inquiry #4: There is no gradation spec for item #36, Precoated Screenings. Please provide.
Inquiry submitted 09/21/2017

Response #1:
Submitted for consideration.
Response posted 09/21/2017


Response #2:
Refer to Section 37-2.05B(1)(d)(iii)(D) of the Standard Specifications. Bid per current contract documents.
Response posted 09/22/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.