Viewing inquiries for 06-0S3404

Submit new inquiry for this project


Inquiry #1: Where is the removal of the existing Concrete median located on Highway 198 and Road 180 to be paid, as the quantity sheets do not appear to address it in either of the concrete removal items or the Roadway Ex quantities shown in the summary of quantities sheets.

Inquiry submitted 09/19/2017

Response #1:
Submitted for consideration.
Response posted 09/19/2017




Inquiry #2: In stage 1 Phase 1 the contractor is to widen the outside shoulder of the existing East bound lanes near station 220+00 to near 419+00. The stage construction and traffic handling plans do not show any K-Rail being placed on the outside shoulder in order to complete this work. The typical cross sections for this area show Road Ex, AB and HMA to be placed. This will require more than a 12 hour closure window in order to complete. Will the state please add in the required quantity of K-rail to do this work.
Inquiry submitted 09/22/2017

Response #1:
Submitted for consideration.
Response posted 09/22/2017


Response #2:
Bid per current contract documents.
Response posted 09/22/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.