Inquiry #1: The spec for the slurry seal reads to use a continuous self-loading mixing machine.Would the State consider changing to the use of truck mount slurry machines instead?
Inquiry submitted 04/07/2017

Response #1:Submitted for consideration.
Response posted 04/10/2017


Response #2:No. Particularly on the travelled way and shoulders.

Contractor may use truck mounted slurry machines only on these locations:
1. Radii
2. Side streets
3. Gore areas
4. Areas requiring hand work

Response posted 04/12/2017




Inquiry #2: The specs only allow a 0.2 mile closure for the reversing traffic control on the project. This does not allow the contractor to be efficient with a truck mount or a continuous machine. All this will do is increase the cost and days of production of the project do to all of the downtime that the crews will have. Would the state consider lengthening the closure?
Inquiry submitted 04/10/2017

Response #1:Submitted for consideration.
Response posted 04/12/2017


Response #2:Lane closure lengths and hours are set by the Office of Traffic Safety. No changes will be made.
Response posted 04/13/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.