Inquiry #1: Is there supposed to be plant establishment for this job?
Specs say plant establishment period is type 1.

Inquiry submitted 09/19/2013

Response #1:09/19/13: Your inquiry has been received and is being reviewed. Thank you for your patience.
Response posted 09/19/2013


Response #2:09/19/13: Your question is being taken under consideration. Unless an addendum is issued addressing your concern, please bid per the current contract documents.
Response posted 09/19/2013


Response #3: 9/20/13: Please refer to Addendum No. 1. In the Special Provisions, Section 20-9 is deleted.
Response posted 09/20/2013






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.03, “Examination of Plans, Specifications, Contract, and Site of Work,” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.