Inquiry #1: Refer to sheet 121 construction note 1 and 2. Please confirm the total assembly will be relocated as is. Plans are not clear on scope.
Inquiry submitted 12/11/2017

Response #1:Submitted for consideration.
Response posted 12/11/2017


Response #2:The total assembly will not be relocated. Please refer to legend 1, remove count station cabinet and foundation. Remove as defined by the Standard Specification on page 12. Please refer to legend 2, relocate the equipment for the count station into a new count station cabinet and foundation as shown in E-1. Refer to the ED-1 (page 127) and section 86-1.02Q(3) page 49 of the Special Provision for count station cabinet. Refer to RSP ES-3C for the new cabinet foundation.


Response posted 12/11/2017


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.