Inquiry #1: There is no HMA bid item. How is payment made for the HMA paving around the ADA ramps?
Inquiry submitted 10/30/2017

Response #1:There is no HMA paving around the curb-ramps. Removal of any concrete gutter should be done by saw cutting (as shown on the plans) without damaging the adjacent asphalt pavement if any.


Response posted 10/31/2017




Inquiry #2: REFER TO SHEET 190. THE WORK SHOWN ON ALL "E" PLAN SHEETS DOES NOT CORRELATE WITH THE WORK AND QUANTITIES SHOWN ON SHEET 190. PLEASE CLARIFY.
Inquiry submitted 11/01/2017

Response #1:Please, specify which electrical plans do not match on sheet 190 (Quantity Sheet Plan).
Response posted 11/02/2017




Inquiry #3: THE "E" SHEETS HAVE CONFLICTING OR CONFUSION CONSTRUCTION NOTES COMPARED TO THE POLE AND EQUIPMENT SCHEDULES CAUSING AMBIGUITY AND THE SHEET 190 DOES NOT HELP EITHER. PLEASE CLARIFY
Inquiry submitted 11/01/2017

Response #1:Please specify which construction notes cause ambiguity.
Response posted 11/02/2017




Inquiry #4: How deep is the Aerially Deposit Lead since excavations may vary and may affect other work too? Please clarify.
Inquiry submitted 11/02/2017

Response #1:Excavations will be 3 to 10 inches deep from top of existing soil.
Response posted 11/02/2017




Inquiry #5: Regarding Inquiry #2 Response: as a typical example, refer to plan 165 shows 6 ea and sheet 190 shows 2 ea.

Regarding Inquiry #3 Response: as typical example, refer to plan sheet 164. Pole and equipment schedule only requires the PPBA Post as new ("N" noted) with the rest to remain existing and the drawings show different.

Inquiry submitted 11/02/2017

Response #1:Please bid per contract plans and special provisions.
Response posted 11/02/2017


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.