Inquiry #1: BID ITEM 26 APPEARS TO HAVE AN ERROR IN THE UNIT OF MEASURE -
UNIT OF MEASURE IS CURRENTLY BY THE LB. SHOULD BE MEASURED BY THE CY.
PLEASE MAKE NOTE OF THE ERROR AND PROVIDE A NEW BID ITEM LIST.

Inquiry submitted 12/19/2017

Response #1:Submitted for consideration.
Response posted 12/19/2017


Response #2:See Addendum 1.
Response posted 01/26/2018




Inquiry #2: No answer has been provided for the initial inquiry dated 12/19/17. This job bids in two weeks.
Please address the inquiry so that we can properly bid the minor concrete item.

Inquiry submitted 01/15/2018

Response #1:Submitted for consideration.
Response posted 01/16/2018


Response #2:Inquiry withdrawn.
Response posted 01/26/2018




Inquiry #3: I retract my earlier inquiry of today. It appears all bid item quantities & units of measure are conformed.
Inquiry submitted 01/15/2018

Response #1:Noted.
Response posted 01/16/2018




Inquiry #4: Under Section 12 - Temp Traffic Control, it states that for each 10-minute infraction past the time to open the closure, the Contractor will be assessed 5% of the total bid amount for each infraction.

Your EE is $840,000. 5% of this number (total bid) = $42,000 for each infraction for the 1st 1/2 hour and double that for one hour.
This is totally unreasonable. Under the Standard Specs for Liquidated Damages, a job of this size would be subject to no more than $1,900 per day for going over each day of the contract time in total. $42,000 / $1,900 = 22 times more punitive than going over contract time.

Please consider amending the LD's for lane closure infractions to a more reasonable value that is representative of the cost to the public.

Inquiry submitted 01/26/2018

Response #1:Submitted for consideration.
Response posted 01/26/2018


Response #2:There are no Liquidated Damages. Please defer to the table Under Section 12.
Response posted 01/30/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.