Flag Canyon Creek Bridge Replacement Phase 2


DESCRIPTION

Replace the existing span with a 100-footlong bridge.

PROJECT BENEFITS

This project upgrades the Highway 70 crossing over Flag Canyon Creek with a new bridge, providing wider, eight-foot shoulders for vehicles.

FUNDING BREAKDOWN

State - $3,400,000
Federal - $0
Total - $3,400,000

PROJECT SCHEDULE

Environmental Document Completed - June 2013
Right of Way Acquisition Completed - July 2014
Design Completed - August 2014
Advertise: November 2014
Begin Construction: April 2015
Expected Completion: January 2017

PARTNERSHIP

none

PROJECT CONTACT

Rodney Murphy, Project Manager
Phone: (530) 741-5127
Email: rodney.murphy@dot.ca.gov

Gilbert Mohtes-Chan, Public Information Officer
Phone: (530) 741-4571
Email: gilbert.mohtes-chan@dot.ca.gov

NO ADDITIONAL DOCUMENTS AVAILABLE

NO NEWS AVAILABLE

NO ADDITIONAL PHOTOS OR VIDEOS AVAILABLE


News

Contact Information

General Information:

Phone: (530) 741-4572
Fax: (530) 741-4111

Physical Address:

California Department of Transportation
District 3
703 B Street
Marysville, CA 95901

Caltrans Logo

Translate.