Interstate 80 Mountain Section Striping Project


DESCRIPTION

This project will remove existing 4-inch traffic striping and replace with 6-inch traffic striping on Interstate 80 from Colfax to the Nevada state line. The project also will replace traffic markers with “wrong way” markers.


PROJECT BENEFITS

The wider traffic stripes will be more visible to the traveling public and autonomous vehicles. Traffic stripes will be more visible in inclement weather. The “Wrong Way” pavement markers will provide a more continuous reflection warning to wrong way drivers.


FUNDING BREAKDOWN

The support and capital components are being funded through the Major Maintenance Program using SB 1 funding.

COST ESTIMATE:
Support Cost: $2,100,000
Capital Cost: $16,179,000
Total Project Cost: $18,279,000


PROJECT SCHEDULE

Project Approval & Environmental Document -- 10/11/17
Design Completed -- 1/02/18
Advertise Project -- 1/22/18
Begin Construction -- 6/1/18
Complete Construction -- 10/31/18
End Construction -- 2/1/19

PARTNERSHIP

none

PROJECT CONTACT

Sameh Hegazi, Project Manager
Phone: (530) 741-4319
Email: sameh.hegazi@dot.ca.gov

Steve Nelson, Public Information Officer
Phone: (530) 741-4566
Email: steve.nelson@dot.ca.gov

NO DOCUMENTS AVAILABLE

NO NEWS AVAILABLE

NO ADDITIONAL PHOTOS OR VIDEOS AVAILABLE


News

Contact Information

General Information:

Phone: (530) 741-4572
Fax: (530) 741-4111

Physical Address:

California Department of Transportation
District 3
703 B Street
Marysville, CA 95901

Caltrans Logo

Translate