Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 2 3 7 1 13
Number of Advanced Deliveries 1 0 3 0 4
Construction Value
($ Millions)
$16.4 $73.3 $74.8 $0.2 $164.8

District 2 commits to the deliveries by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Brian F. Crane, District 2 Director, on 7/27/07

Signed by, Will Kempton, Director, on 7/27/07