Restoring the Golden State

District 1
Contract for Delivery
FY 2006/2007

Ready to List (RTL) Milestone Delivery
Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 2 3 6 2 13
Number of Advanced Deliveries 0 2 1 1 4
Construction Value
($ Millions)
$7.2 $11.9 $27.1 $6.8 $53.0

District 1 commits to the delivery by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Charles Fielder, District 1 Director, on 6/22/06

Signed by, Will Kempton, Director, on 6/22/06

Attachment: 2006/2007 FY Project RTL Baseline Delivery Plan