Description 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Total
Number of Planned Deliveries 9 10 6 0 25
Number of Advanced Deliveries 0 0 0 3 3
Construction Value
($ Millions)
$19.9 $31.9 $31.4 $76.6 $159.8

District 11 commits to the delivery by quarter of the projects listed by Ready to List (RTL) milestones and dollar values as shown above.

Signed by, Pedro Orso-Delgado, District 11 Director, on 6/22/06

Signed by, Will Kempton, Director, on 6/22/06

Attachment: 2006/2007 FY Project RTL Baseline Delivery Plan