Dept. of Trans. PROGRESS Serial No. Contract No. 10-357-07-08 12-0E0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-15.1/16.4 Federal Project: NONE Progress payment No. 29 Payment period ending: 12-20-10 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING SUITE 200 IRVINE CA 92618 Escrow No. 02398 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,438,287.66 18,060.00 2.a. Extra Work 483,915.52 16,386.20 b. Adjustment Comp. -172,898.51 0.00 3. Materials on Hand 198,283.92 0.00 4. Earned Subject to Retention 10,947,588.59 34,446.20 5. Mobilization 1,260,000.00 0.00 6. Total Work Completed 12,009,304.67 7. Deductions -1,102.50 0.00 8. a.Contract Retentions -547,379.43 -1,722.31 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,659,106.66 32,723.89 10. Reduction Amt to Escrow 11. Payment to Escrow 547,370.00 12. Net Pymt. this Estimate 32,723.89