Dept. of Trans. PROGRESS Serial No. Contract No. 12-082-14-56 11-2E0064 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 29% 11-SD-56-3.5/3.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 03-20-12 PACIFIC RESTORATION GROUP INC P O BOX 429 PERRIS CA 92572 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 138,860.33 130,975.33 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 138,860.33 130,975.33 5. Mobilization 56,250.00 56,250.00 6. Total Work Completed 195,110.33 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 195,110.33 187,225.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 187,225.33