Dept. of Trans. PROGRESS Serial No. Contract No. 10-263-08-24 09-2144U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 96% 09-INY-395-65.0/76.1 Federal Project: NONE Progress payment No. 25 Payment period ending: 09-20-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 02414 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,080,085.78 626,690.65 2.a. Extra Work 1,308,417.76 3,602.50 b. Adjustment Comp. -450,004.38 0.00 3. Materials on Hand 4. Earned Subject to Retention 34,938,499.16 630,293.15 5. Mobilization 3,530,395.00 0.00 6. Total Work Completed 38,468,894.16 7. Deductions -866.60 0.00 8. a.Contract Retentions -1,746,924.96 -31,514.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 36,721,102.60 598,778.49 10. Reduction Amt to Escrow 11. Payment to Escrow 1,746,920.00 12. Net Pymt. this Estimate 598,778.49