Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-239-10-18 07-4K6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-60-11.2/11.2 Federal Project: NONE Progress payment No. 11 Payment period ending: 08-10-07 ODONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 02270 Total Estimate This Estimate 1. Contract Itms Without Mobil. 768,217.21 9,210.00 2.a. Extra Work 37,164.70 4,967.57 b. Adjustment Comp. 16,888.71 -1,005.00 3. Materials on Hand 4. Earned Subject to Retention 822,270.62 13,172.57 5. Mobilization 52,000.00 0.00 6. Total Work Completed 874,270.62 7. Deductions 8. a.Contract Retentions -40,454.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 40,454.90 40,454.90 9. Total pay to Contractor 874,270.62 53,627.47 10. Reduction Amt to Escrow -40,170.00 -40,170.00 11. Payment to Escrow 40,170.00 12. Net Pymt. this Estimate 13,457.47