Dept. of Trans. PROGRESS Serial No. Contract No. 12-264-13-49 07-2159C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 16% 07-LA-5-1.8/3.0 Federal Project: IMOO-5294(9N) Progress payment No. 11 Payment period ending: 09-20-12 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MAROCS CA 90278 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,360,591.01 311,694.60 2.a. Extra Work 376,871.90 40,944.25 b. Adjustment Comp. 3. Materials on Hand 16,377,835.76 10,460,612.70 4. Earned Subject to Retention 20,115,298.67 10,813,251.55 5. Mobilization 5,700,000.00 1,200,000.00 6. Total Work Completed 9,437,462.91 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,815,298.67 12,013,251.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,013,251.55