Dept. of Trans. FINAL Serial No. Contract No. 07-338-08-21 07-1Y4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-210-22.4/24.6 Federal Project: NONE Progress payment No. 06 Payment period ending: 09-18-07 ORTIZ ASPHALT PAVING INC P O BOX 883 COLTON CA 92324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 574,813.56 0.00 2.a. Extra Work b. Adjustment Comp. 13,425.17 13,425.17 3. Materials on Hand 4. Earned Subject to Retention 588,238.73 13,425.17 5. Mobilization 62,972.61 0.00 6. Total Work Completed 651,211.34 7. Deductions 8. a.Contract Retentions -27,948.88 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 27,948.88 0.00 9. Total pay to Contractor 651,211.34 13,425.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,425.17