Dept. of Trans. PROGRESS Serial No. Contract No. 03-170-06-41 06-342424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 32% 06-FRE-180-R60.3/R64.0 Federal Project: ACNH-P180(44) Progress payment No. 10 Payment period ending: 06-20-03 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 02019 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,349,061.43 1,333,983.60 2.a. Extra Work 258,165.82 95,078.55 b. Adjustment Comp. 163,739.87 -5,127.20 3. Materials on Hand 779,606.16 150,118.97 4. Earned Subject to Retention 14,550,573.28 1,574,053.92 5. Mobilization 4,655,000.00 0.00 6. Total Work Completed 18,425,967.12 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -905,869.99 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,299,703.29 1,584,053.92 10. Reduction Amt to Escrow 11. Payment to Escrow 905,860.00 12. Net Pymt. this Estimate 1,584,053.92