Dept. of Trans. PROGRESS Serial No. Contract No. 03-055-13-28 06-342424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 18% 06-FRE-180-R60.3/R64.0 Federal Project: ACNH-P180(44) Progress payment No. 06 Payment period ending: 02-20-03 E L YEAGER CONSTRUCTION COMPANY INC P O BOX 87 RIVERSIDE CA 925020087 Escrow No. 02019 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,143,130.78 1,021,048.50 2.a. Extra Work 130,716.35 1,825.92 b. Adjustment Comp. 111,583.50 -14,416.50 3. Materials on Hand 410,847.07 0.00 4. Earned Subject to Retention 6,796,277.70 1,008,457.92 5. Mobilization 3,675,000.00 0.00 6. Total Work Completed 10,060,430.63 7. Deductions 8. a.Contract Retentions -679,627.77 -100,845.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,791,649.93 907,612.13 10. Reduction Amt to Escrow 11. Payment to Escrow 500,000.00 12. Net Pymt. this Estimate 907,612.13