Dept. of Trans. PROGRESS Serial No. Contract No. 11-332-12-47 04-1SS244 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 95% 04-ALA-680-0.3 Federal Project: 04-ALA-680-0.3/0.3 NONE Progress payment No. 04 Payment period ending: 11-20-11 REDGWICK CONSTRUCTION COMPANY 8150 ENTERPRISE DRIVE NEWARK, CA 94560 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,600.00 0.00 2.a. Extra Work 783,653.42 100,394.05 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 792,253.42 100,394.05 5. Mobilization 6. Total Work Completed 792,253.42 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 792,253.42 100,394.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,394.05