Dept. of Trans. PROGRESS Serial No. Contract No. 11-081-14-31 04-1E6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 55% 04-CC-80-11.2/ .0 Federal Project: 04-SON-101-50.3/ .0 NONE 04-MRN-101-7.6/20.7 Progress payment No. 01 Payment period ending: 03-20-11 REPUBLIC INTELLIGENT TRANSPORTATION SERVICES INC 371 BEL MARIN KEYS BL NO 200 NOVATO CA 94949 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 368,360.00 368,360.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 368,360.00 368,360.00 5. Mobilization 6. Total Work Completed 368,360.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 368,360.00 368,360.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 368,360.00