Dept. of Trans. PROGRESS Serial No. Contract No. 09-166-14-12 03-4C7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 18% 03-COL-16-R4.4/4.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 06-19-09 REGE CONSTRUCTION INC 600 SANTANA DRIVE CLOVERDALE CA 95425 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 955.43 955.43 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 955.43 955.43 5. Mobilization 6. Total Work Completed 955.43 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 955.43 955.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 955.43