Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-10-57 03-0A6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 90% 03-SIE-49-16.9/41.4 Federal Project: ACST-PP04(915) Progress payment No. 05 Payment period ending: 08-20-12 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,655,049.33 2,875,054.29 2.a. Extra Work 198,507.53 86,093.03 b. Adjustment Comp. 319,422.96 238,493.36 3. Materials on Hand 121,123.99 121,123.99 4. Earned Subject to Retention 15,294,103.81 3,320,764.67 5. Mobilization 330,000.00 0.00 6. Total Work Completed 15,502,979.82 7. Deductions -15,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,609,103.81 3,315,764.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,315,764.67