Quarterly Review of Inactive Projects
Frequently Asked Questions

  1. What projects are subject to inactive quarterly review?

    Inactive projects as defined in question # 1 are subject to quarterly review based on FHWA criteria listed below

    1. Projects inactive for the past 12 months with unexpended balances more than $500,000,
    2. Projects inactive for the past 24 months with unexpended balances of $50,000 to $500,000, and
    3. Projects inactive for the past 36 months with unexpended balances less than $50,000