California Department of Transportation
 

Contract 09-338104

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Road is currently closed for the season. How can we do a site visit?

A1) Due to the winter conditions, no site visit is available. 4Jan11.


Q2) The cold foam contractors are concerned that they cannot visit the site due to road closure. The project gets widened into native material, and the existing structural section handout with the contract documents does not clarify the material outside of the existing structural section Suggest postpone bid opening to facilitate site visit after road opens.

A2) Bid opening will not be extended or rescheduled. 7Jan11.


Q3) Can the bid date for this project be postponed because route 270 is currently closed for winter and bidding contractors cannot access or see the project due to the snow?

A3) The bid date cannot be delayed enough to make a site visit feasible. Document your inability to visit the jobsite, and any assumptions made due to that inability, in your bid documents, and rely on the bid package and any other available information for your bidding purposes. 10Jan11.