Contract 05-0K7504

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q1) Based on sheet 9 of 23 Construction Area Signs sign #2, the public is being advised that pavement ends. Will the Contractor be allowed to have the public travel on a gravel surface during construction operations? There is a direct conflict between the plan details and specifications, therefore, based on order of precedence the detail prevails. Please clarify

A1) Yeas, the contractor will be allowed to run traffic on a gravel surface.