California Department of Transportation
 

Contract (05A1875)

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1)Section 86-610d list to clean and paint Department-furnished Model 334LC changeable message sign cabinets and back and sides of Department furnished message sign. My understanding is that the sign is new and furnished by the department. Is this referring to touch up paint for these items or a complete paint job?

A1)Per current contract documents, “sign cabinets and back and sides of Department-furnished changeable message sign” should be “clean(ed) and paint(ed)". 13Apr16