California Department of Transportation
 

Contract 10-0Y8204(10A1769)

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Inquiry 1.) For the invert paving, Minor concrete- can we use shotcrete?  Shotcrete was used on several other job that I know of for this type of work. 9Mar16

Response 1.) Use minor concrete, refer to page 4 of the plan sheet .11Mar16


Inquiry 2.)For the welded wire for the invert paving what are we required to use for the tac welding.  Do we use the nelson studs or can we tac weld the wire to the culvert? 9Mar16

Response 2.) , The plan didn’t specify type of tack welding, but it requires the wire fabric to be tack welded to the culvert every 4” transversely and 30” longitudinally, refer to page 4 of the plan sheet.11Mar16