- Caltrans Statewide
- District 4 Home Page
- District 4 Departments
- Organizational Chart
- Contact District 4
I-880 Menu
GIS Search Map

92/880 Interchange Reconstruction Project
- Project Overview | Powerpoint
14MB

- District 4 Lane Closures
- Project Photos - Page 1 | Project Photos - Page 2
- Public Flyer April 2, 2008
- Public Information Notice May/June 2008
- Public Information Notice March/April 2008
- Public Information Notice Feb/March 2008
- Public Flyer February 28, 2008
The Route 92/Interstate 880 (I-880) Interchange Reconstruction Project is the reconstruction of the four (4) quadrant cloverleaf interchange by modifying the interchange to include multi-lane direct connectors from:
- Route 92 eastbound to I-880 northbound
- Route 92 westbound to I-880 southbound
The project boundaries are on I-880 just north of the Tennyson Road Overcrossing to just south of the Winton Ave Overcrossing and on Route 92 west of the Mount Eden Overhead to just east of Santa Clara Street.
Below are Before and After simulations:

Construction Schedule and Phasing
Construction for the Route 92/I-880 Interchange Project began October of 2007. The duration of the project construction is projected to last 48 months.
