
|
The schedule for the East Span Project is based on several decisions, beginning with the design and environmental review process. Assuming the East Span Project is able to move forward as planned, Caltrans has prepared the following target schedule: |
|
Project Timeline |
|
|
Federal Register Notice of Intent for EIS |
April 21, 1997 |
|
Public Scoping Meetings |
Spring 1997 |
|
Public Information Open Houses |
December 1997, March 1998 |
|
Recommendation of Final Design Concept from MTC |
April 1998 |
|
Draft EIS Released |
September 1998 |
|
Public Hearings/Formal Comment Period |
September - November 1998 |
|
Caltrans Identifies Preferred Alternative |
December 1998 |
|
Dredged Material Management Plan Released |
June 1999 |
|
Supplemental Draft Section 4(f) Evaluation Released |
June 1999 |
|
May 2001 |
|
|
Record of Decision Filed (Target date) |
Summer 2001 |
|
Final Design and Contracting (Target date) |
2002 |
|
2002 - 2007 |
|