| Contract No.... |
Location |
Description |
Advertise Date |
Bid Opening |
| BID OPENING FOR LAST 30 DAYS |
|
04-1A6814
|
Ala-880-28.2/29.9 |
Replace Concrete Pavement (rapid Strength Concrete).
|
07/19/10 |
10/05/10 |
|
04-0A8724
|
SM-1,35,82,84,101,etc.-Var |
Upgrade The Barrier And Guardrail End Terminals
|
07/26/10 |
10/12/10 |
|
04-4876A4
|
SCl-101-39.8/40.6 |
Replacement Highway Planting
|
08/02/10 |
10/13/10 |
|
04-4A07U4
|
Ala-580-R4.7/R8.2 |
Const Truck Climbing Lane, Ret. Walls, And Rehab Traveled Way
|
03/05/12 |
04/25/12 |
|
04-292264
|
Ala-80-2.5/3.3 |
Construct Multi-purpose Trail & Bikeway,with Ret Wall.
|
03/12/12 |
05/01/12 |
|
04-2E2704
|
Son-12-T18.5/18.8 |
Cold Plane Asphalt Concrete And Bonded Wearing Course Overlay
|
03/19/12 |
04/24/12 |
|
04-3E1004
|
Ala-185-5.3/5.7 |
Cold Plane Pavement And Place Hot Mix Asphalt (type A).
|
03/19/12 |
04/24/12 |
|
04-283824
|
Son-116-41.8/44.7 |
Creek Realignment, Install Plants And Irrigation, Establish Planting
|
04/02/12 |
05/15/12 |
|
04-2E0704
|
SCl-82-14.3/19.2 |
Cold Plane And Place Hot Mix Asphalt (open Graded).
|
04/02/12 |
04/25/12 |
|
04-2E5104
|
Mrn-1-0.0/13.0 |
Bonded Wearing Course (gap Graded) Overlay
|
04/09/12 |
05/02/12 |
|
04-2E6504
|
Nap-121-9.4/22.0 |
Cold Plane And Overlay With Rubberized Hot Mix (gap Graded)
|
04/09/12 |
05/02/12 |
|
04-2E5404
|
SM-82-0.0/2.7 |
Cold Plane Pavement And Overlay With Bonded Wearing Course
|
04/16/12 |
05/08/12 |
|
04-2E5504
|
SM,SCl-35-0.0/21.0 |
Place Asphalt-rubber Seal Coat
|
04/16/12 |
05/16/12 |
|
04-2E5604
|
SM-101-12.0/13.5 |
Hot Mix Asphalt (bonded Wearing Course -gap Graded) Overlay
|
04/16/12 |
05/15/12 |
|
04-2E5304
|
Son-1-30.5/50.6 |
Bonded Wearing Course Overlay.
|
04/16/12 |
05/09/12 |
|
04-2G6304
|
SM-280-9.6/10.5 |
Cold Plane Pavement And Place Rubberized Hot Mix Asphalt (gap Graded).
|
04/16/12 |
05/09/12 |
|
04-3A7204
|
SM-1-35.9 |
Install Left Turn Channelization Lane
|
04/16/12 |
05/08/12 |
|
04-2G5904
|
Ala,SCl-85,101,880-44.0, 19.9, 20.8 |
Replace Damaged Overhead Signs.
|
04/23/12 |
05/15/12 |
|
04-2E7704
|
Ala,SF,SM,SCl,Sol,Son-17,24,37,80,87,etc-Var |
Upgrade Xenon Cms To Led Modules
|
04/23/12 |
05/16/12 |
| BID OPENING FOR THE NEXT 6 MONTHS |
| DVBE Notice |
|
04-0120T4
|
SF-80-12.6/13.9 |
Construct Bridge, Roadways, Electrical, Buildings And Remove Bridges
|
04/09/12 |
09/25/12 |
.
The responses to bidder' inquiries, unless incorporated into a formal addenda to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder' inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.