Description
This project proposes to construct a new interchange at the intersection of Highway 99 and Highway 113 in the Tudor area of Sutter County.
Project Benefits
The purpose of this project is to improve traffic operations and safety.
Funding Breakdown
Local - N/A
State - $19.4 mil ($17.8 mil Proposition 1B)
Federal - N/A
Estimated Total Project Cost - $19.4 million
Project Schedule
Environmental Document Completed -- March 12, 2004
Right of Way Acquisition Completed -- June 7, 2012
Design Completed -- June 18, 2012
Advertise -- July 16, 2012
Begin Construction -- May 1, 2013
Expected Construction -- December 1, 2014
Partnership
Caltrans, Sacramento Area Council of Governments and Sutter County
Project Contact
Winder Bajwa, Caltrans Project Manager (530) 741-4432 email: winder_bajwa@dot.ca.gov
Gilbert Mohtes-Chan, Public Information Officer (530) 741-4571 email: gilbert_mohtes-chan@dot.ca.gov
Workshop 1 Tuesday, May 3, 2011 5:00 p.m. to 7:00 p.m. Belle Cooledge Library, Community Room 5600 South Land Park Drive, Sacramento |
Workshop 2 Wednesday, May 4, 2011 5:00 p.m. to 7:00 p.m. Joseph Sims Elementary School, Multipurpose Room 3033 Buckmaster Drive, Elk Grove |
Public Notice (
258Kb)
Yolo, and Sacramento Counties - (530) 741-5474
Nevada, Placer, and Sierra Counties - (530) 634-7640
El Dorado County or the Tahoe Basin - (530) 741-4566