W/X VIADUCT ON U.S. 50 REHABILITATION PROJECT

Description
The W/X Viaduct on US 50 lies between 18th Street and 24th Street. It is two 2,530 foot-long structures carry six lanes of traffic over city streets, freight, and light rail lines in downtown Sacramento. Built in 1968, they have extensive cracking on the deck and are in need of rehabilitation in order to enhance safety, reduce recurring maintenance costs, and increase the life of the concrete decks. Caltrans repair strategy involves placing a 4-inch concrete deck on top of the existing and treating it with a protective coating of methacrylate, as well as steel column casings for seismic strengthening.

Project Benefits
The service life of the structure decks will be extended to about 20 years, which will significantly reduce maintenance expenditures. The completed project will also provide widening at the shoulders, new joint seals, new concrete barriers and railing, standard lighting, and enhanced safety.

Funding Breakdown
Local - n/a
State - $46,205,000
Federal - included in State costs
Estimated Total Project Cost - $46,205,000 (capital and support)

Project Schedule
Environmental Document Completed -- August 2012
Right of Way Acquisition Completed -- n/a
Design Completed -- February 2013
Advertise -- May 2013
Begin Construction -- Eastbound Phase 1-- April 22 - May 21 and Westbound Phase 2 -- May 27 - June 25
Expected Completion -- Winter 2014

Partnership
Caltrans, City of Sacramento, County of Sacramento, SACOG

Project Contact
Rodney Murphy, Project Manager 530-741-5127 email: rodney.murphy@dot.ca.gov
Dennis Keaton, Public Information Officer (530) 741-5474 email: dennis.keaton@dot.ca.gov

Updated 4-3-14

project map

 

W/X VIADUCT ON U.S. 50 REHABILITATION PROJECT

Stage 1 Work

Stage 1- Detour for Closure of 11th St. On Ramp and 16th St. On Ramp to EB Route 50

Stage 1 - Closure of 11th St. On Ramp and 16th St. On Ramp - Detour to NB Route 51/Business 80

Stage 1 - Closure of 11th St. On Ramp and 16th St. On Ramp - Detour to SB Route 99

Stage 1 - Detour for Closure of EB 50 to SB99 Connector

Stage 1 - Detour for Closure of EB 50 to NB 51/SB 99 Connector

Stage 1 - Detour for Closure of NB Route 5 Connector Ramp to EB Route 50

Stage 2 Work

Stage 2 - Detour for Closure of NB Route 99 Connector to WB Route 50 and closure of SB Route 51 to WB Route 50 Connector

Stage 2 - Detour for Closure of NB Route 99 Connector to WB Route 50 and closure of SB Route 51 to WB Route 50 Connector

 

W/X VIADUCT ON U.S. 50 REHABILITATION PROJECT

W/X VIADUCT ON U.S. 50 REHABILITATION PROJECT

Below is the schedule of upcoming Milestones for W/X Viaduct rehabilitation project
 
Advertise - 05/13/13
Bids Open - 07/17/13

Construction is scheduled to start Summer 2014 and is scheduled to end Winter 2014. Actual lane shift closures for US50 will be done next construction season (Summer 2014).