project information
area recreation
- During the five-year construction, there will be some inconvenience to recreational activities and traffic. However, Antlers Boat Ramp will remain open and lake access through the construction zone will be maintained.
- Visitors Guide
- Camping at Shasta Lake
- Recreation.Gov
- Shasta-Trinity National Forest
related
I-5 Antlers Bridge Replacement
For the week of February 8, 2010
The contractor continues to build a trestle in and around the Pier 5 location on the north side of the lake. The increase in water level has inundated the Pier 4 location, but the rising water levels did not beat the hard work and determination by Tutor Saliba crews near Pier 5. The trestle piles near Pier 5 have all been extended and they are currently working on erecting bracing, floor beams and stringers in preparation for the concrete deck panels currently planned to be set in a few weeks. The construction of the concrete batch plant that will provide the concrete for the bridge is near complete. Work continues on final assembly along with electrical and plumbing necessities.
This page will offer periodic updates on construction progress and alert the community to upcoming stages, which may impact the traveling public. For additional information, or If you would like to be alerted via e-mail when information is updated, please contact:
Denise_Yergenson@dot.ca.gov (530) 225-3260
| Timeline: Design: Completed January 2009 Advertised: May 18, 2009 Bids Opened: August 4, 2009 Awarded: September 25, 2009 Began Construction: November, 2009 Completion Date: 2014 |
Contact Information: Public Information Office (530) 225-3260 |

