I-5 Antlers Bridge Replacement

I-5 Antlers Bridge Replacement Proposed Antler's Bridge Proposed Realignment Construction Staging Area

Area Traffic Cameras

Antlers CCTV
Antlers Traffic Camera
 

For the week of February 8, 2010

The contractor continues to build a trestle in and around the Pier 5 location on the north side of the lake. The increase in water level has inundated the Pier 4 location, but the rising water levels did not beat the hard work and determination by Tutor Saliba crews near Pier 5. The trestle piles near Pier 5 have all been extended and they are currently working on erecting bracing, floor beams and stringers in preparation for the concrete deck panels currently planned to be set in a few weeks. The construction of the concrete batch plant that will provide the concrete for the bridge is near complete. Work continues on final assembly along with electrical and plumbing necessities.

This page will offer periodic updates on construction progress and alert the community to upcoming stages, which may impact the traveling public. For additional information, or If you would like to be alerted via e-mail when information is updated, please contact:
Denise_Yergenson@dot.ca.gov (530) 225-3260

Milestones/Timeline
Timeline:
Design: Completed January 2009
Advertised: May 18, 2009
Bids Opened: August 4, 2009
Awarded: September 25, 2009
Began Construction: November, 2009
Completion Date: 2014
Contact Information:
Public Information Office (530) 225-3260