Welcome to California California Home
Welcome to California - images of Golden Gate Bridge, ocean sunset, waterfall, flowers, and city skyline
Caltrans Home
District 12 Home
District 12 Overview
Press Releases
Community Events
Local Assistance Program
Orange County Construction Activity
OC Construction Projects
Seven Day Road Closure Plan
Orange County Traffic Information
Statewide Traffic Information
Statewide Right of Way Excess Land Program
Contact District 12
ALT Information Here
 District 12 Orange County

 My CA     This Site 
  

Caltrans > Local Sites > D12 internet > OC Construction Projects > SR-55 Improvement Project >
SR-55 Project Timeline & Cost

SR-55 Project Timeline & Cost

Project Timeline

Construction of the SR-55 North Improvement Project began in January 1999 and will be completed on schedule in 2002.

How much does all this cost?

The total SR-55 North Improvement Project will cost over $118 million over a three-year period, from 1999 to 2002.

How is the SR-55 North Improvement Project funded?

The primary source of funding for the SR-55 North Improvement Project is the California State Transportation Improvement Program (STIP). In addition, the City of Orange contributed $5 million for improvements to Katella, La Veta and Meats Avenues. Beyond this, $21 million for project design and right-of-way acquisition was funded through Measure M, the half-cent transportation sales tax Orange County voters approved in 1990.

The project is managed jointly through a partnership between Caltrans and the Orange County Transportation Authority (OCTA). Together, both organizations are working hard to make the SR-55 a safe and smooth-flowing freeway that will meet our transportation needs well into the 21st Century.

Project Features
Project Background & History
Project Timeline & Cost
Press Releases & Construction Updates
Project Photos
SR-55 Frequently Asked Questions