 |
San Diego - Coronado Bridge Seismic Retrofit Schedule
March 1999
Project One
Description:
Retrofit toll main span superstructure
Begin/End construction:
Under Construction (Winter 1997)/Fall 1998
Est. cost:
$3.5 million
Project Two
Description:
Retrofit tower and foundation. Piers 2
- 24 and abutment (Coronado side)
Begin/End Construction:
Spring 1999/Summer 2001
Est. cost:
$48 million
Project Three
Description:
Retrofit tower and foundation. Piers 25-32
Begin/End construction:
Fall 1998/Winter 1999
Est. cost:
$5 million
Project Four
Description:
Retrofit approach ramps (San Diego side)
Begin /End construction:
Fall 1998/Winter 2000
Est. cost:
$14 million
Estimated total construction cost: $70.5 million
|
 |