| CONTRACT NO: | 11-185944 |
| ROUTE / KP | 11-SD-5/78-R81.8/R82.4, 0.0/1.0 |
| LOCATION | In
San Diego County In Carlsbad And Oceanside On Route 5 From 0.1 Km South
Of Buena Vista Creek Bridge To Route 5/78 Separation And On Route 78 From
5/78 Separation To Jefferson Street Overcrossing. |
| DESCRIPTION | Existing Highway To Be Widened. |
| ESTIMATE | $ 3,277,000.00 |
| ADVERTISE DATE | 07/23/01 |
| BID OPENING | 08/23/01 |
| FINAL POSTING | 08/22/01 @ 15:00 |
|
|
HAZARD CONSTRUCTION | $ 2,367,856.00 |
|
|
ORTIZ | $ 2,397,777.00 |
|
|
NICHOLAS GRANT CORP | $ 2,668,821.00 |
The Caltrans District 11
Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing
address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11 Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the contract,
are not a part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a summary
of the matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that Contract,
but reserves the right to not answer any questions deemed unsatisfactory
for public viewing.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously and all attempts will be made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
08/09/01 |
|
|
BIDDER'S
INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
Q:07/24/01 R:08/06/01 |
Plan Sheet /
Specification Reference=NOTICE TO CONTRACTORS
When will the cross sections be available and where?
or through: MESA
BLUEPRINT
|
|
Q:08/06/01 R:08/06/01 |
Plan Sheet /
Specification Reference=NOTICE TO CONTRACTORS
Are full size plans available?
or through: MESA
BLUEPRINT
|
|
Q:08/06/01 R:08/08/01 |
Plan Sheet /
Specification Reference=Item 5:TEMPORARY CRASH CUSHION (ADIEM-350), Special
Provisions Section 10-1.49
The engineer's estimate shows 5 EA, but the staging plans call out for the use of only 2 at any given stage and the Specials state that "A move of the temporary crash cushion (ADIEM-350) will be paid for as extra work as provided in Section 4-1.03D of the Standard Specifications and the temporary crash cushion (ADIEM-350) will not be counted for payment in the new position." Is the engineer's estimate correct?
|
|
Q:08/08/01 R:08/20/01 |
Plan Sheet /
Specification Reference=Traffic Chart No. 13, Section 10-1.15 LATE REOPENING
OF CLOSURES
Does the late reopening penalty of closures apply to this chart?
|
|
Q:08/08/01 R:08/20/01 |
Plan Sheet /
Specification Reference=Plan sheet 84 of 128
The plans show the relocation of sign structure no 4 on west bound 78. There are no traffic charts that allow the closure of west bound 78. Will the be an additional chart to allow the closure of 78 to do all this work?
In the opinion of the Engineer a minor deviation to perform a traffic break by the CHP for the final placement of the sign structures will better serve public traffic and also expedite the work. Written request shall be submitted to the Resident Engineer for approval of the traffic break plan. |
|
Q:08/08/01 R:08/20/01 |
Plan Sheet /
Specification Reference=Plan sheet 84 of 128
The plans show the installation of sign structure no 5 on east bound 78. There are no traffic charts that allow the closure of east bound 78. Will there be an additional chart to allow the closure of 78 to do all this work?
In the opinion of the Engineer a minor deviation to perform a traffic break by the CHP for the final placement of the sign structures will better serve public traffic and also expedite the work. Written request shall be submitted to the Resident Engineer for approval of the traffic break plan. |
|
Q:08/08/01 R:08/20/01 |
Plan Sheet /
Specification Reference=Plan sheet 92 of 128 and 127 of 128
There is a conflict between the diameter of the sign foundation pile as shown on page 92 and the pile diameter as called out by the post type and referenced to page 127 of the plans. Under which item is the incorrect pile size to be paid?
|
|
Q:08/10/01 R:08/20/01 |
Plan Sheet /
Specification Reference=Plan sheet 94 of 128 and Item 48:Architectural
Texture
Is there a layout available for the architectural treatment as shown on the retaining wall?
|
|
Q:08/15/01 R:08/22/01 |
Plan Sheet /
Specification Reference= Contract Item 73, Special Provisions Section
10-1.47, Standard Plan A76 and Contract Plan Sheets 2, 3, 10 - 17.
Please provide accurate pavement differential elevations for grades, eastbound and westbound, at intersection of concrete barrier face with finish pavement grade. This is necessary to accurately determine concrete and rebar quantification and extent of lower #13 rebar stirrups required by Standard Plan A76, Note 9, where pavement differential is 305 MM (12") or greater. Due to variable width and variable cross slope of asphalt concrete shoulders, and because no profile grades are provided for eastbound direction Station 10+07 to 11+73, accurate pavement differentials cannot be calculated. |
|
Q:08/15/01 R:08/20/01 |
Plan Sheet /
Specification Reference= Reference Plan Sheets 88, 89 and 92.
Signs 4 and 5 are noted to " . . . extend piles to top of barrier." Please clarify if the extension is to be within the upper pedestal portion of CIDH foundation (Standard Plan S-13, Section B-B), or is the extension to occur in the lower portion, (Section A-A on Standard Plan S-13.)
|
|
Q:08/16/01 R:08/22/01 |
Plan Sheet /
Specification Reference= Section 10-1.34 ARCHITECTURAL SURFACE (TEXTURED
CONCRETE)
Where can we view the referee sample?
|
|
Q:08/17/01 R:08/20/01 |
Plan Sheet /
Specification Reference= Special Provisions Section 10-1.14, Lane Chart
#13, Section 10-1.15, Special Provisions Section 10-1.36.
Request the State provide responsible full freeway lane closure period on Rte. 5 northbound. Work required by Special Provisions for Sign Structure No. 1, cannot be performed safely and in workmanlike manner with only 10 minute traffic breaks.
|
|
Q:08/17/01 R:08/20/01 |
Plan Sheet /
Specification Reference= Layout Plan Sheet 7 (L-3).
Clarify the location of Type 60E Concrete Barrier. New Sign #5 left leg is at Station 14+28.5 "SD 78 A." No type 60E Barrier has been provided for at this location.
|
|
Q:08/17/01 R:08/22/01 |
Plan Sheet /
Specification Reference= Special Provisions Section 10-1.14, Chart
#9.
Can a Chart be provided to permit single lane closure (2 lane ramp) in lieu of full ramp closure shown on Chart #9.
|
|
Q:08/17/01 R:08/22/01 |
Plan Sheet /
Specification Reference= Plan Sheets 2, 3, 6, 7, 53 and 54.
At what Stations will the full 9.8 M work area be available as shown in "Typical Section" sheet 53 and 54. The cross sections and layout sheets apparently do not provide this information. |