BIDDER'S INQUIRIES & RESPONSES
DISTRICT 11 CONSTRUCTION


CONTRACT NO: 11-2T0974
ROUTE / PM 11-SD-15, 163-M11.2/M14.5,R10.8/R11.1
LOCATION In San Diego County In San Diego On Route 15 From 0.3 Mile South Of H Avenue Overcrossing To 0.2 Mile North Of Pomerado Road Overcrossing And On Route 163 From Kearny Villa Road Overcrossing To Route 163/15 Separation.
DESCRIPTION Install Planting, Erosion Control And Automatic Irrigation Systems.
ESTIMATE $2,660,000
WORKING DAYS

950

ADVERTISE DATE 09/06/2011
BID OPENING 10/13/2011
FINAL POSTING
10/13/2011@ 10:25

Bid Summary

The Caltrans District 11 Office is located at 4050 Taylor Street, San Diego, CA 92110. The District 11 Duty Senior telephone number is (619) 688-6635. Please submit all inquiries in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to bidder' inquiries, unless incorporated into a formal addenda to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The availability or use of information provided in the responses to bidder' inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.
Caltrans District 11 Construction Department has developed this method of answering Bidder's Inquiries to better serve the needs of the Contractors who bid on our Projects. Caltrans District 11 Construction Department will post all of the questions submitted by any of the contractors that are registered Planholders for that Contract, but reserves the right to not answer any questions deemed unsatisfactory for public viewing.
The BIDDER'S INQUIRIES & RESPONSES will be updated continuously and all attempts will be made to do the final posting by 15:00 on the day prior to the bid opening.


INFORMATION AVAILABLE



BID ITEMS
 SPECIALS
PLANS
 PLANHOLDERS
 



ORDERING PROJECT PLANS AND SPECIFICATIONS   

3% DVBE Requirement * Cost per set: Bidders: $E-ad, Non-bidders: $E-ad


ADDENDUM



 

BIDDER'S INQUIRY SUBMITTAL FORM


Inquiry No.
Inquiry

   1

  Q:10/12/11
R:10/13/11

Plan Sheet / Specification Reference= Section 4 Beginning of Work, Time of Completion and Liguidated Damages, the 1st working day is the 15th day after contract approval.

Question= Can the 1st working day be extended to start 55 days after contract approval? Fifteen days is not enough time to submit SWPPP, schedule, and other submittals.

  • The 1st working day of the contract will not be changed.  Please bid per the current  contract documents..
   

 


OTHER LINKS OF INTEREST

DISTRICT 11 CONSTRUCTION BIDDER'S INQUIRIES & RESPONSES
DISTRICT 11 HOMEPAGE
CALTRANS OFFICE ENGINEER: Contract Advertisement, Special Provisions, Plan Holders, Contract Awards, etc.
DEPARTMENT OF TRANSPORTATION