| CONTRACT NO: | 11-281604 |
| ROUTE / KP | 11-SD-5702 |
| LOCATION | In San Diego County In El Cajon At Bostonia Maintenance Station At 1463 East Broadway |
| DESCRIPTION | Remediation
Of Hydrocarbon Contaminated Soils. |
| ESTIMATE | $450,000 |
| WORKING
DAYS |
90 |
| ADVERTISE DATE | 04/27/2009 |
| BID OPENING | 5/29/2009, 5/28/2009 |
| FINAL POSTING |
05/27/09
@ 15:00 Hrs
|
The Caltrans District
11
Office is located at 4050 Taylor Street, San Diego, CA 92110. The
District 11
Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract,
are not a part of the contract and are provided for the bidder's
convenience
only. In some instances, the question and answer may represent a
summary
of the matters discussed rather than a word-for-word recitation. The
responses
may be considered along with all other information furnished to
prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is
not
to be construed in any way as a waiver of the provisions of Section
2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements.
Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction
Department
has developed this method of answering Bidder's Inquiries to better
serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that
Contract,
but reserves the right to not answer any questions deemed
unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES
& RESPONSES will be updated continuously and all attempts will be
made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
| Materials Information Handout |
|
|
|
|
ORDERING
PROJECT PLANS AND SPECIFICATIONS
ADDENDUM
| Addendum
1, Plan Sheets |
|
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1 Q:04/27/09 |
Plan Sheet / Specification
Reference= license requirements do you mean an General Engineering A license or c-12 with a hazardous substances endorsement? or sometimes referred to as an "haz" endorsement. technically. there is no such thing as a "A hazardous"
|
|
2 Q:05/06/09 |
Plan Sheet / Specification
Reference= license requirements Question=will there be a site
walk, if so when and where?
|
| 3 Q:05/13/09 |
Plan Sheet / Specification
Reference= 17, Roadway Excavation (Hydrocarbon Contaminated), Plan
Sheet C-1, Section 10-1.15 Question: Cross Section A-A and B-B show a 15'feet deep excavtion with vertical sidewalls and no shoring shown. Is the State expecting vertical sidewalls and therefore, shoring? Or can the sidewalls be sloped to safe thus increasing quanaties of HMA and possibly import?
|
| 4 Q:05/14/09 R:05/14/09 |
Plan Sheet / Specification
Reference=General Question:Will subsurface information be made available?
|
| 5 Q:05/15/09 R:05/18/09 |
Plan Sheet / Specification
Reference= Question:Does this project require any of the large diameter auger borings as suggested in the Kleinfelder “Corrective Action Plan” dated December 16, 2004 or is this primarily an excavation project within the 40’ X 46’ area of concern as indicated in the Secor International, Inc. “Corrective Action Plan Addendum” dated January 4, 2007? Secor International, Inc. addendum report indicated 30’ X 40’ excavation area – please advise.
|
| 6 Q:05/15/09 R:05/18/09 |
Plan Sheet / Specification
Reference= Question: From the layout offered in the plans it does NOT appear like the excavation extends into the roadway (East Broadway) – Is this correct? And if so what traffic control is required? I see traffic control specifications are provided can you be any more specific??
|
| 7 Q:05/15/09 R:05/18/09 |
Plan Sheet / Specification
Reference= Question:As specified in Section 10-1.14 Earthwork is “Reinforcement or metal attached to reinforced concrete rubble placed in embankments shall not protrude above the grading plane” indicative of shoring/tight-sheeting around four (4) sides of the excavation? Please specify as it is not clear in either Section 10-1.14 or 10-1.15 or Section 19 “Earthwork.”.
|
| 8 Q:05/15/09 R:05/18/09 |
Plan Sheet / Specification
Reference= Question: I realize that soil contaminated with hydrocarbons will undergo waste characterization analysis BUT for bidding purposes how should liquids and solid waste streams be classified? Based on benzene concentrations solid wastes most likely will either be “non-RCRA hazardous waste (State of CA regulated)” or “Hazardous waste solids (D018)” Would assume more or less the same for waste liquids.
|
| 9 Q:05/20/09 R:05/20/09 |
Plan Sheet / Specification
Reference= Addendum 1 Question: It is my understanding that an addendum has been issued. Is this true?
|
| 10 Q:05/21/09 R:05/22/09 |
Plan Sheet / Specification
Reference= General Question: The scope of work is slated for excavation for the remediation process. Will other methodologies be considered such as bio-remediation (Not Bio Venting or Spray and Pray but active control of the remediation process? If so then how would you like us to proceed with our bid?
|
| 11 Q:05/22/09 R:05/27/09 |
Plan Sheet / Specification
Reference=Corrective Action Plan, Amendment dated 2007 by Secor Question: The Corrective Action Management Plan by Secor indicates that three trenches will be excavated to a depth of 12 feet below grade and backfilled with one sack sand/cement slurry to 6 feet below grade. Is this a requirement of the contract?
|
| 12 Q:05/22/09 R:05/27/09 |
Plan Sheet / Specification
Reference=Dewatering Question: Is it anticipated that the contractor shall completely dewater the excavation or just remove whatever water is capable of being extracted from the dewatering well. Regardless, the excavation may remain saturated depending on the actual amount of groundwater encountered, and therefore, difficult to obtain 90% compaction effort. Please clarify.
|
| 13 Q:05/22/09 R:05/27/09 |
Plan Sheet / Specification
Reference= Section 10-1.15, Stockpiling of excavated material. Plan
Sheet L-1 Question: 1) Can the tree in the middle of the property be cut down and removed?
3) What will be done with the overhead utilities-primarily telephone in the area designated for the new drive? Can the building immediately west of the proposed new drive be removed also, along with the metal shed, to provide a wider berth onto the property?
4) Will the sidewalk need to be closed for the duration of the project and will the bus stop near the proposed new drive need to be moved?
|
| 14 Q:05/26/09 R:05/27/09 |
Plan Sheet / Specification
Reference= Section 10-3 Signals, Lighting & Electrical Systems,
Page 40, Subheading 10-3.02, Maintaining Existing Traffic Management
System Elements during Construction. Question: 1) Are there any TMS elements within the project limits? Of so, where?
2) Should an allotment be made for pre-constrcution operational status check? If so, how much?
|
| 15 Q:05/26/09 R:05/27/09 |
Plan Sheet / Specification Reference=Item Number 17 Roadway Excavation (Hydrocarbon Contamtination) Question: Question=These Questions were submitted on May 18, 2009. There have not been posted to the website. Here they are again.:
1. The Cross Sections A-A and B-B indicate that 618 cubic yards and 341 cubic yards of reusable and contaminated soils respectively will be excavated. However the stockpile areas indicated on Layout L-1 will only accommodate approximately 200 cubic yards and 30 cubic yards respectively. Please indicate how this discrepancy is proposed to be handled by the State.
2. In Special Provision 10-1.15 Stockpiling of Excavated Material it is indicated that the stockpile material shall be on two layers of 1-inch thick (minimum) black polyethylene and shall be covered by 1-thick (minimum) black polyethylene. It appears that the thickness is a mistake. It is not practical to obtain and use 1-thick polyethylene sheeting. Please clarify this issue.
3. In Special Provision 10-1.15 Sampling and Analysis Requirements the type of testing to be conducted is outlined, but no indication of the quantity of samples that should be taken and tested is provided. In addition, no standards with respect as to what is acceptable for reuse are provided other than the statement that “contamination concentrations are less than levels requiring special handling and disposal by applicable regulatory agencies”. Since the listed “applicable” regulatory agencies have different standards depending on site end-use and exposure risks, please provide guidance on these issues for bidding.
4. The Special Provisions and Plans do not indicate sampling of the excavation sidewalls or bottom to verify that all of the contaminated materials have been removed. Is testing of the excavation sidewalls and bottom going to be required of the Contractor or is the State planning to conduct the testing itself?
5. By virtue of the dewatering system it is anticipated that during the excavation water will be encountered. This will lead to a soft excavation bottom. The Special Provisions in Section 10-1.14 exclude the use of man-made materials for stabilization of the bottom. This implies a gravel or rock bottom stabilization. Please provide guidance on what is acceptable backfill stabilization and to what height above the water-impacted bottom does the stabilized material need to extend.
|
|
16
Q:05/26/09 R:05/27/09 |
Plan Sheet / Specification
Reference= 17, Roadway Excavation (Hydrocarbon Contaminated), Plan
Sheet C-1, Section 10-1.15 Question: 1) It is probable that workers will have to work in the bottom of the excavation. Safe sloping is not possible because of existing conditions. Shoring will likely be necessary. Under what line item will the shoring be paid?
3) Can we expand the designated stockpile areas where possible and needed?
|
|
17
Q:05/XX/09 R:XX/XX/XX |
Plan Sheet / Specification
Reference= Question: |
OTHER LINKS OF INTEREST
DISTRICT 11 CONSTRUCTION
BIDDER'S INQUIRIES & RESPONSES
DISTRICT 11 HOMEPAGE
CALTRANS OFFICE ENGINEER:
Contract Advertisement, Special Provisions, Plan Holders, Contract
Awards, etc.
DEPARTMENT OF TRANSPORTATION