| CONTRACT NO: | 11-075804 |
| ROUTE / KP | 11-SD-5-R32.5/R38.7 |
| LOCATION | In San Diego County In San Diego From 0.2 km North Of San Diego River Bridge To 0.2 km North Of The Mission Bay Drive Overcrossing. |
| DESCRIPTION | Construct Median Barrier. |
| ESTIMATE | $ 6,332,000.00 |
| ADVERTISE DATE | 06/10/02 |
| BID OPENING | |
| FINAL POSTING | 07/22/02 @ 17:00 |
|
|
HAZARD CONSTRUCTION, INC | $ 3,707,838.00 |
|
|
DALEY - CCAC, JV | $ 4,142,603.00 |
|
|
MODERN ALLOYS, INC | $ 4,809,392.60 |
The Caltrans District 11 Office is located at 2829
Juan Street, San Diego, CA 92110. The mailing address is P.O. Box 85406,
San Diego, CA 92186-5406. The District 11 Duty Senior telephone number
is (619) 688-6635. Please submit all inquiries in the proper format by
fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to bidder' inquiries,
unless incorporated into a formal addenda to the contract, are not a part
of the contract and are provided for the bidder's convenience only. In
some instances, the question and answer may represent a summary of the
matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department has
developed this method of answering Bidder's Inquiries to better serve the
needs of the Contractors who bid on our Projects. Caltrans District 11
Construction Department will post all of the questions submitted by any
of the contractors that are registered Planholders for that Contract, but
reserves the right to not answer any questions deemed unsatisfactory for
public viewing.
The BIDDER'S INQUIRIES &
RESPONSES will be updated continuously and all attempts will be made to
do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
Aerially Deposited Lead State Route 5 between the San Diego River Bridge and 0.2 km North of the Mission Bay Overcrossing. |
|
ADDENDUM
|
07/09/02 |
|
|
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
Q:06/18/02 R:07/03/02 |
Plan Sheet
/ Specification Reference=Notice to Contractors, Page 2
When will cross sections be available and from where?
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 |
|
Q:06/21/02 R:07/01/02 |
Plan Sheet / Specification
Reference= 38 THRU 43- CONCRETE BARRIER , TYPE 60 SERIES - VARIOUS PLANS,
SPECIAL PROVISION SECTION10-1.42
DOES THE DEPARTMENT'S DESIGN FEEL THAT THIS BARRIER WILL BE EXPOSED TO WEATHER OR OTHER CONDITIONS THAT JUSTIFY THE ADDED EXPENSE OF EPOXY COATED REINFORCING STEEL? PLEASE REVIEW AND CONFIRM , OR PROVIDE AN ADDENDUM TO DELETE EPOXY COATING.
|
|
Q:06/24/02 R:07/03/02 |
Plan Sheet / Specification
Reference= Items 38 thru 43, TYPE 60 BARRIERS, L-1 thru L-16, page 111
SPECIAL PROVISION SECTION10-1.42
Bar reinforcing for use in barriers shall be epoxy coated prefabricated reinforcement conforming to Section 52 "Reinforcement," of the Standard Specifications. Request for verification. Is epoxy coating required?
|
|
Q:06/28/02 R:07/03/02 |
Plan Sheet / Specification
Reference=Item # 17 Remove Traffic Stripe ( Yellow ). (See special
Provisions Page # 94)
Has any decision been made as to the "Yellow Paint removal" Quantity which appears to be incorrect based on the fact that the median shoulders were repaved and (repainted with "lead free" paint last year). Additionally it does not appear necessary to remove the yellow lines since they will be behind K-Rail and would only need to be repainted at the end of the project.
|
|
Q:07/03/02 R:07/03/02 |
Plan Sheet / Specification
Reference=Bid item 10 K-Rail and Sheets 49-54 Traffic Handling Plans
Will Caltrans allow project, and therefore K-Rail, to be constructed in sections or phases so that access will not be limited and quantity of K-Rail required at one time will not be so great?
|
|
Q:07/11/02 R:07/22/02 |
Plan Sheet
/ Specification Reference=Section 10-1.01 "Order of Work", Addendum 1
Portion of Addendum 1 regarding Section 10-1.01 "Order of Work" states southbound side must be complete prior to commencing work on the Northbound side. Will Caltrans also allow contractor to construct each side in sections thereby allowing better access, reducing K-Rail required, and shortening length of area without shoulder?
|
|
|
|
OTHER LINKS OF
INTEREST
DISTRICT
11 CONSTRUCTION BIDDER'S INQUIRIES & RESPONSES