| CONTRACT NO: | 11-080514 |
| ROUTE / KP | 11-SD-5,15,67,805-VAR |
| LOCATION | In San Diego County At Various Locations. |
| DESCRIPTION | Park And Ride Pavement Rehabilitation. |
| ESTIMATE | $ 510,000 |
| ADVERTISE DATE | 05/08/2006 |
| BID OPENING | 06/08/2006 |
| FINAL POSTING | 06/07/06 @ 15:45 |
| 1 |
SIM J. HARRIS INC. | $385,385.00 |
| 2 |
HAZARD CONSTRUCTION | $402,454.00 |
| 3 |
KIRK PAVING INC | $435,947.00 |
| 4 |
DALEY CORP | $460,342.25 |
| 5 |
ABC CONSTRUCTION | $501,255.00 |
| 6 |
ZONDIROS CORP | $582,565.00 |
| 7 |
RAMONA PAVING & CONST CORP | $588,770.00 |
The Caltrans District 11
Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing
address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11
Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract,
are not a part of the contract and are provided for the bidder's
convenience
only. In some instances, the question and answer may represent a
summary
of the matters discussed rather than a word-for-word recitation. The
responses
may be considered along with all other information furnished to
prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is
not
to be construed in any way as a waiver of the provisions of Section
2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements.
Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction
Department
has developed this method of answering Bidder's Inquiries to better
serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that
Contract,
but reserves the right to not answer any questions deemed
unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES
& RESPONSES will be updated continuously and all attempts will be
made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
|
|
|
|
BIDDER'S
INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
Q:05/26/06 |
Plan
Sheet / Specification Reference=Item 6 "Traffic Control System",
Section 10-1.09 Maintaining Traffic
Item 11 "Coldplane", Special Provisions Page 123 Coldplane Asphalt Concrete Item 17 "Replace AC Surfacing, Section 10-1.19 Replace Asphalt Concrete Surfacing Question=1) What are the allowed working hours for this project? 2) Are the Park & Rides to remain open to the Public during non-working hours? 3) The coldplaning specification states that the paving shall be completed within the same shift as the coldplaning. Is this a necessary requirement for this type of project? 4) The Provisions state that the outline of the asphalt concrete to be removed shall be sawcut. At the Contractor's option, will the State allow removal by coldplane method?
|
|
|
Plan Sheet / Specification Reference= Question= 1)- In general
my question
have to do with closing down the parking lots during
construction.
There are no special lane closure charts or lot closures charts
identifying
closure hours or complete closure grouping of days , without this data
may we assume complete closure is at our discretion and that 24 hr
closure
will be allowed during cold plan, exc-earthwork, concrete, paving and
seal
coat items of work.
|