Rehabilitate Bridge Decks.
Advertise Date
11/15/99
Bids Open
12/16/99
The responses to bidder' inquiries, unless incorporated into a formal addenda to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The availability or use of information provided in the responses to bidder' inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.
Caltrans District 11 Construction Department has developed this method of answering Bidders Inquiries to better serve the needs of the Contractors who bid on our Projects.
The BIDDER'S INQUIRIES & RESPONSES will be updated continuously with the last posting no later than 15:00 on Wednesday prior to the bid opening.
Caltrans District 11 Construction Department will post all of the questions submitted by any of the registered Planholders for that Contract, but reserves the right not to answer any questions deemed unsatisfactory for public viewing.
|
|
Inquiry |
|
|
The quantities for Item 14 calculate lower than shown in the Engineer's
Estimate. Please clarify.
Bid it as you you see it. |
|
|
Section 4 of the Special provisions states completion before expiration
of 80 working days. However 10-1.06 Maintaining Traffic allows only 14
calendar days at each location. With only three locations this works out
to only 30 working days. How should this be interpreted?
Each location is either the left or the right side of the roadway per each bridge, and work may be done concurrently for completion within the allowed contract time. |