| CONTRACT NO: | 11-2326U4 |
| ROUTE / KP | 11-SD-15-M27.8/M30.7 |
| LOCATION | In San Diego County In San Diego From Mercy Road Undercrossing To 0.6 Km South Of The Route 56/15 Separation. |
| DESCRIPTION | Construct Added And Auxiliary Lanes, Ramp Widening, Bridge Widening And Retrofit. |
| ESTIMATE | $ 13,500,000.00 |
| ADVERTISE DATE | 02/02/04 |
| BID OPENING | |
| FINAL POSTING | 04/14/04 @ 15:35 |
|
|
FCI CONSTRUCTORS, INC. | $15,344,700.00 |
|
|
DIABLO CONSTRUCTORS, INC. | $15,424,796.00 |
|
|
COFFMAN SPECIALTIES, INC. | $16,645,000.00 |
The Caltrans District 11 Office is located at 2829
Juan Street, San Diego, CA 92110. The mailing address is P.O. Box 85406,
San Diego, CA 92186-5406. The District 11 Duty Senior telephone number
is (619) 688-6635. Please submit all inquiries in the proper format by
fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to bidder' inquiries,
unless incorporated into a formal addenda to the contract, are not a part
of the contract and are provided for the bidder's convenience only. In
some instances, the question and answer may represent a summary of the
matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department has
developed this method of answering Bidder's Inquiries to better serve the
needs of the Contractors who bid on our Projects. Caltrans District 11
Construction Department will post all of the questions submitted by any
of the contractors that are registered Planholders for that Contract, but
reserves the right to not answer any questions deemed unsatisfactory for
public viewing.
The BIDDER'S INQUIRIES &
RESPONSES will be updated continuously and all attempts will be made to
do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
|
|
|
SECTIONS |
|
|
|
|
|
BIDDER'S INQUIRY SUBMITTAL
FORM
|
|
Inquiry |
|
Q:02/10/04 |
Plan Sheet /
Specification Reference=NOTICE TO CONTRACTORS
When will the cross sections be available and where?
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com San Diego, CA 92123 |
|
Q:03/04/04 |
Plan Sheet /
Specification Reference=
Plan sheet 24 indicates the entire Los Penasquitos Creek as an ESA area. Will a crossing be allowed. Secondly, bent 4 is shown within the ESA area. Please review.
|
|
Q:03/16/04 |
Plan Sheet /
Specification Reference=77 Structure Concrete Bridge Plan Sheet
No. 169-230
On various precast girder projects, the State, on occasion, has allowed the use of stay in place (STIP) metal decking as an alternative in the Contract Special Provisions. At the same time, precast girder projects have been completed with (STIP) metal decking when in fact it was not listed as an alternative in the Contract Special Provisons. Will stay in place metal decking be allowed on this project?
|
|
Q:03/19/04 |
Plan Sheet /
Specification Reference=Plan sheet L-1/L-3
Question=Will the frontage road right of the Caltrans R/W be available for access to the work at Los Penasquitos Creek?
|
|
Q:03/19/04 R:03/25/04 |
Plan Sheet /
Specification Reference=Plan Sheet L-6/L-8
Question=It appears that a majority of the planned work from station 308+/- to the end of work has been completed. What are the changes as a result of this circumstance?
|
|
Q:03/19/04 |
Plan Sheet /
Specification R eference= Item #40 & Sheet Q-1 Quantity Summary
Question=Plan sheet Q-1 indicates a total quantity of 11607 M3 for roadway excavation, but Bid Item #40 (Roadway Excavation) is a quantity of 7810 M3. Please clarify.
|
|
Q:03/24/04 R:04/05/04 |
Plan Sheet /
Specification Reference= Coordination
Site review indicates that there may be an existing fiber optic line in the area of the SB 15 widening north and south of the Los Penasquitos bridge. This utility is not shown on the plans or discussed in the special provisions. Please review.
|
|
Q:03/24/04 R:04/01/04 |
Plan Sheet /
Specification Reference=1,2,3)Layout sheet L-3. 4) Sheet #129 (HP-1).
1) Will we be
allowed to use the frontage road (and the existing lower arched
Los
|
|
Q:03/24/04 |
Plan Sheet /
Specification Reference= 86(S), Elastomeric Bearing Pads for
Precast Concrete Girders. Plan number 222 of 237. On the contract plan, pier cap detail, the bearing pads are specified as 100mm thick. Is this correct?
|
|
Q:03/24/04 |
Plan Sheet /
Specification Reference= 86(S), Bearing Pads for Precast
Concrete Girders, plan number 201 of 237. Bearing Pad Detail
on the plan shows galv. sheet metal on top of
|
|
Q:03/24/04 |
Plan Sheet /
Specification Reference= 86(S), Prestressed I Girders. Plan
sheet number 226 of 237. Section C-C on
the plan shows 6 #43 rebars at the bottom of the
|
|
Q:03/24/04 |
Plan Sheet /
Specification Reference=Item #68 Concrete Pavement
Bid item #68 indicates 2420cm of concrete pavement..actual take off and quantity sheet Q-1 actually show in excess of 3600cm of concrete pavement. Is there and adendum being issued regarding this item?
|
|
Q:03/25/04 |
Plan Sheet /
Specification Reference=EARTHWORK - Roadway Embankment
Sheet Q-1 Under Earthwork Quantities, there appears to be 7581 CM of Embankment from SB "SD-15" STA 300+15 to 302+64; however, there seems to be no work between these stations. What happens between these stations to provide this amount of Embankment?
|
|
Q:03/26/04 |
Plan Sheet /
Specification Reference=
1)Are "As-Builts" construction documents available for our review? 2)Are there any additional Geotechnical information pertinent or specific to the site available for review including but not limited to: previous investigation(s), historical geologic maps, logs, etc.? 3)Our site review noted that there are different rock types in the vicinity of the existing structures. Is there any data or information identifying the rock quality including but not limited to: rock type, consistency, rock competence, hardness, permeability (fracture permeability or otherwise), fracture patterns, etc.? 4)What subsurface conditions should be anticipated at each pile location when drilling in the natural overburden? Same question applies to when drilling in the man-placed shot rock fill? 5)Water was observed flowing in Penasquitos Creek; can we anticipate water in any of the CIDH excavations? If so, at what volume and / or rate of infiltration? At what elevation or depth? Which piles might / would be affected? 6)If it is necessary to stabilize the upper portion (overburden) of the CIDH pile will the installation of a permanent CMP liner be permitted? We anticipate that if allowed, this CMP will need to extend a nominal depth into the rock. 7)What type of
tooling can we anticipate to be appropriate for the anticipated rock drilling
or coring referred to in the Special Provisions?
|
|
Q:03/30/04 |
Plan Sheet /
Specification Reference=1) PAGE 92 OF THE SPECIAL CONDITIONS (SECTION 5-1.2
MIGRATORY BIRDS)
1)Swallows were observed nesting in the existing columns as of 3-29-04. Will we be allowed to work during the nesting season if no nests are visible? Will we be able to work during the nesting season if swallows are inside the columns? If swallows are
observed outside of the nesting season, & inside the columns
|
|
Q:04/07/04 |
Plan Sheet /
Specification Reference= L-3
Existing chain link fence that runs under the Los Penasquitos bridge that is not on the right of way will be destroyed by the planned work, and is not shown to be replaced. Will this need to be replaced, and if so how will it be paid for?
|
|
Q:04/07/04 |
Plan Sheet /
Specification Reference=Contract plan sheets 204 & 222
Reference is made to the pour staging on the pier cap detail and note#1. Is it safe to assume that the falsework for the pier cap loading is for the cap construction alone, or do the loads of the precast girder and the concrete deck need to be taken into account.
|
|
Q:04/14/04 |
Plan Sheet /
Specification Reference= Prestressed I Girders
Question: Is it acceptable to lift and place new prestressed I girders using cranes set up on existing bridge structure? Attached drawing shows set up locations and outrigger loadings. Main load bearing (rear) outriggers to be located on pile cap beams and front outrigger loads to be spread over two girders by means of crane mats.
|
|
Q:04/14/04 |
Plan Sheet /
Specification Reference=Bid Item 104 thru 107 Alternative Pipe Culvert
Sheet 53, D-19
Question=The Alternate
Pipe table at the bottom of sheet 53 calls out Corrugated Steel Pipe as
an allowable Alternative Pipe, the Gage of material & coating (if required)
is not specified.
|