| CONTRACT NO: | 11-0301U4 |
| ROUTE / KP | 11-SD-5, 805 & 56-R45.5/R59.5,41.4/46.3 &T0.7/T2.0 |
| LOCATION | In San Diego County. |
| DESCRIPTION | Freeway
And Four Bridges To Be Widened With Four Bridges To Be Constructed,
A Plantable Geosynthetic Reinforced Wall, And Retaining Walls To Be Built With Drainage And Electrical Work. |
| ESTIMATE | $ 121,141,000.00 |
| ADVERTISE DATE | 10/01/01 |
| BID OPENING | |
| FINAL POSTING | 01/23/02 @ 17:00 |
|
|
E L YEAGER CONST INC | $ 109,174,194.60 |
|
|
SHIMMICK / OBAYASHI JV | $ 112,262,933.00 |
|
|
FCI CONSTRUCTORS, INC | $ 112,379,361.60 |
|
|
RADOS, INC / MCM | $ 118,719,157.50 |
|
|
GRANITE / CC MEYERS JV | $ 125,429,660.30 |
|
|
BALFOUR BEATTY CONST INC | $ 127,312,940.50 |
|
|
KIEWIT PACIFIC CO | $ 129,158,305.00 |
The Caltrans District 11
Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing
address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11 Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the contract,
are not a part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a summary
of the matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered planholders for that Contract,
but reserves the right to not answer any questions deemed unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES & RESPONSES will be updated continuously and all attempts
will be made to do the final posting by 17:00 on Wednesday prior
to the bid opening.
|
|
|
|
|
|
|
|
|
SEE NEW REVISED INFO 01/08/02 |
ADDENDA
|
11/20/01 |
12/28/01 |
01/10/02 |
01/15/02 |
BIDDER'S
INQUIRY SUBMITTAL FORM
|
|
Inquiryhttp://www.dot.ca.gov/hq/esc/oe/project_ads_addenda/11/11-0301U4/ |
|
Q:10/01/01 R:11/10/01 R:11/26/01 |
Plan Sheet /
Specification Reference=NOTICE TO CONTRACTORS
When will the cross sections be available and where?
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com San Diego, CA 92123 |
|
Q:10/04/01 R:11/09/01 |
Plan Sheet /
Specification Reference=NOTICE TO CONTRACTORS
When and how will we be able to obtain cross section electronic files for this upcoming bid? Will they be available on CD or downloaded from the internet or e-mail?
|
|
Q:10/08/01 R:12/18/01 |
Plan Sheet /
Specification Reference=Section 10-1.39 PLANTABLE GEOSYNTHETIC WALL
Will the State accept proposals to use another proprietary wall?
|
|
Q:10/09/01 R:10/09/01 |
Plan Sheet /
Specification Reference=
Is there a local printing firm to order full size plans from?
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com |
|
Q:10/11/01 R:10/12/01 R:12/28/01 |
Plan Sheet /
Specification Reference=RETENTION
As a potential
DBE subcontractor on the 5-56-805 project we are concerned with regard
to the payment of retentions on this contract. It is the practice of the
industry for General Contractors to pay retentions to subcontractors only
when they are paid - i.e. at the completion of the project. In this case
CALTRANS will not pay all retentions until the completion of the seven
year plant establishment period.
Attention is directed to the provisions in Sections 10262 and 10262.5 of the Public Contract Code and Section 7108.5 of the Business and Professions Code concerning prompt payment to subcontractors. Public Contract Code 10262 and 10262.5 Business and Professions Code Section 7108.5 5-1.102
PROMPT PAYMENT OF WITHHELD FUNDS TO SUBCONTRACTORS
|
|
Q:10/16/01 R:12/28/01 |
Plan Sheet /
Specification Reference= Typical Cross Sections - Sheet X-15, Layout
Drawings - Sheet L-18/L-19, Summary of Quantities (Overlay) - Sheet Q-3
There appears to be a conflict between what is shown on the referenced plan sheets with regard to the limits and quantity of asphalt overlay. The stationing does not match, and the quantity on the summary appears to be excessive for the limits shown. Please clarify the limits of construction and thickness of overlay.
|
|
Q:10/25/01 R:12/28/01 |
Plan Sheet /
Specification Reference= Sec. 10-1.39, Plantable Geosynthetic Reinforced
Wall.
Refer to Sec. 10-1.39, Plantable Geosynthetic Reinforced Wall, page 160 of the special provisions. Under High Tenacity Polyester Encapsulated, par. 1 states that the material shall be encapsulated in an acrylic latex coating. The 2001 Geotechnical Fabrics Report "Specifier's Guide" (volume 18, number 9, Dec. 2000) lists 93 polyester geogrids. Of those 93, only 6 are listed as having acrylic latex coating, and 4 of those have apparently been pulled from the marketplace. Most polyester grids are either PVC Impregnated, PVC coated, or sheathed in a polyethylene. Will these coatings be accepted, providing the material conforms to the LTDS criteria?
|
|
Q:10/29/01 R:11/19/01 |
Plan Sheet /
Specification Reference=Bid Opening
We request the bid date for the referenced project be postponed from Dec. 6th to mid January 2002. We request this bid date for the following reasons: A large project for the MTDB - San Diego is bidding during the same time frame as the referenced project. We are very interested in both projects. We have the resources available to bid both projects; but, not during the same time frame. Our focus is to bid projects aggressively, and give the owner the best and most competitive bid pricing possible.
|
|
Q:10/29/01 R:12/18/01 |
Specification Reference= Section 10-1.39
Plantable Geosynthetic Wall, Bid Item # 70: Plantable Geosynthetic Reinforced
Wall, Contract Plan Sheet # 1431 - 1528
The Plantable Geosynthetic Reinforced
Wall shown on the plans appears to be identical to the Tycor Plantable
Retaining walls used on the earlier Caltrans' Interstate 5/56 Widening
project in Del Mar and the more recent SR 125 Freeway project in Lemon
Grove. The Tycor Retaining Wall System is a proprietary
|
|
Q:10/30/01 R:11/05/01 |
Plan Sheet / Specification Reference=Bid
Item #49, Plan Sheets #37 & 542
On Sheet No. 37, Layout L-10, from station 515+63 "SD" to 515+87 "SD" calls for a Type 50 barrier removal. On Sheet No. 542, Summary of Quantities, the same stationing calls for a Type 60E removal. Please clarify.
|
|
Q:10/30/01 R:11/05/01 |
Plan Sheet / Specification Reference=Bid
Item #49, Plan Sheets #37 & 542
On Sheet No. 542, Summary of Quantities, there is a Type 60 barrier removal from Station 535+98 "A" to 536+22 "A" of 24 m. Line A does not go beyond Station 500+00. Please clarify.
|
|
Q:10/30/01 R:11/05/01 |
Plan Sheet / Specification Reference=Bid
Item #49, Plan Sheets #37 & 542
On Sheet No. 542, Summary of Quantities, there is a Type 60 barrier removal from Station 15+89 "SVRM" to Station 16+55 "SVRM" of 66 m. This removal does not exist in the Layout Plans or the Construction Detail Plans. Please clarify.
|
|
Q:10/30/01 R:11/19/01 R:01/06/02 |
Plan Sheet /
Specification Reference=Bid Items 99 & 104, Typical Cross Sections
Sheets 6, 7, 16, 20 & 21
On Typical Cross Section X-5 & 6, Sheet 6 & 7, station 534+31.726 to station 538+70.000 "SB Line", 11.0 m and varies width, placement of 260 mm PCC, 150 mm ACB and 215 mm Class 2 AB. On Typical Cross Section X-15, Sheet 16, station 536+50.339 to station 538+46.751 "SB Line", 11.0 and varies width, placement of 60 mm AC (Type A), 90 mm ACB and 510 mm Class 2 AB. Please clarify what type of material you want placed on the "SB Line" station 536+50.339 to station 538+46.751. Is it PCC or AC?
|
|
Q:10/30/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Bid Items 99 & 104, Typical Cross Sections
Sheets 6, 7, 16, 20 & 21
On Typical Cross Section X-19, Sheet 20, "CMR Line" station 4+22.778 to station 5+64.485, it shows placement of 150 mm AC (Type A) and 495 mm Class 2 AB. Where is this station shown on the Layout Plan?
|
|
Q:10/30/01 R:11/19/01 |
Plan Sheet / Specification Reference=Bid
Items 99 & 104, Typical Cross Sections Sheets 6, 7, 16, 20 & 21
On Typical Cross Section X-20, Sheet 21, "D1 Line" station 11+50 to station 16+50 and "D2 Line" station 11+24 to station 13+86, it shows placement of 150 mm AC (Type A), 165 mm Class 2 AB and 230 mm Class 4 AS. Where is this shown on the Layout Plans?
|
|
Q:10/30/01 R:10/30/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Bid Opening
We request the bid date for the referenced project be postponed from Dec. 6th to mid January 2002. Due to time constraints with a number of projects bidding within the same time frame, we have not as yet had a chance to study the plans in depth. What we have discovered , though, is that there are a number of discrepancies between what is shown on the plans and what is actually in place on the jobsite. We request a bid date extension for this reason. An example of these discrepancies follows: A) As of this date, cross sections are not yet available, and may not be available for some time. We depend heavily on these cross sections in order to complete our take-offs. |
|
Q:10/30/01 R:12/18/01 |
Plan Sheet / Specification Reference=Specification
Section 10-1.39 Plantable Geosynthetic Reinforced Wall
We are in receipt of a faxed letter from TYCOR Retaining Wall Systems regarding this project that reads in part: "To All Contractors, and Planholders for Project 11-0301U4: This letter shall serve as Notice that
the retaining wall design as shown on the drawings published by State of
California, Department of Transportation for the above-mentioned project
is identical, for all intents and purposes, to Tycor retaining wall systems.
Tycor retaining wall systems are protected
Are we obligated to use Tycor Retaining
Wall Systems on this project?
|
|
Q:11/05/01 R:12/18/01 |
Plan Sheet / Specification Reference=Specification
Section 10-1.39 Plantable Geosynthetic Reinforced Wall
We intend to quote the supply of the entire system. We have received a letter indicating that the concrete facing shown in the plans and specifications may infringe on an existing patent. Caltrans details the facing pieces they want in the plans, sheets 1468 and 1469. Will the supplier of the facing system that is exactly as detailed by Caltrans be subject to a patent infringement suit for supplying those pieces?
|
|
Q:11/07/01 R:11/20/01 |
Plan Sheet / Specification Reference=
Bid
Opening
The reason for our inquiry is formally request that the date for bid submission for the referenced project be postponed until the middle of January, 2002. The reasons for our request are due to the late availability of the cross sections, a large number of questions that need to be answered and conflicts with other projects that are scheduled to bid during the first part of December. The analysis of the cross sections is very important for this project in order to properly determine the effects of the phasing on the utilization of the earth materials. We believe it would be in Caltrans best interest to extend the bid date since it would allow the contractors sufficient time to prepare competitive bids. We appreciate your consideration of our request.
|
|
Q:11/07/01 R:11/07/01 R:12/28/01 |
Plan Sheet / Specification Reference=55,
Bridge Removal (Portion), Location D, 1158-1167, 10-1.33 pg 150
Will as-builts for the existing overhangs on Sorrento Valley Viaduct be made available?
|
|
Q:11/07/01 R:12/18/01 |
Plan Sheet / Specification Reference=Specification
Section 10-1.39 Plantable Geosynthetic Reinforced Wall
Caltrans may have inadvertently created
a sole source for this wall. This brings to question the legality of sole
source contracting when Federal funding is provided. This wall is being
presented as a Caltrans design. If so then Caltrans may be according to
the attached statement from Tycor Retaining Wall Systems be guilty of Patent
Infringement. (Standard Specifications 7-1.05).
We are looking forward to clarification on this issue by Addendum.2-1.056 STATE EMPLOYEES AND DESIGN ENGINEERS MAY NOT BID ON CONSTRUCTION CONTRACT
The State's Plantable Geosynthetic Reinforced Wall design as shown in the contract plans and Section 10-1.39 of the Contract Special Provisions was specifically created and designed solely by the State to meet the needs of this project. The State's Plantable Geosynthetic Reinforced Wall design does not infringe upon Tycor Retaining Wall System's design patent no. 6,036,405 or any other existing wall design patents. |
|
Q:11/07/01 R:11/08/01 |
Plan Sheet / Specification Reference=
We would like to take a look at the rock cores obtained during the geotechnical investigation. I would be obliged therefore, if you could advise me where they are located and with whom I should make the necessary arrangements to view them, a telephone number for that person would be appreciated.
a time for him to meet you at the yard. Joe Pratt Office of Geotechnical Services South, Structure Foundations South Branch. Office # is (562) 864-5740, pgr. # (213) 717-6099.
|
|
Q:11/07/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Item 67. Pervious Backfill
Retaining Walls 524, 525 & 531 requires pervious backfill behind the wall. Seems like this was not included in the bid quantity. Will this be paid separately?
|
|
Q:11/07/01 R:01/08/02 |
Plan Sheet / Specification Reference=General
Question Regarding Source of Disposal of surplus dirt.
Your Material Handout says that a material source for excess dirt disposal is at East of I-5 between Del Mar Heights Rd. and Villa De La Valle. Please define this location by showing it on a sketch or address.
LAYOUT01LAYOUT02LAYOUT03
0301u4_DS01.tif 0301u4_DS02.tif 0301u4_DS03.tif 0301u4_DS04.tif 0301u4_DS05.tif 0301u4_DS06.tif 0301u4_DS07.tif 0301u4_DS08.tif 0301u4_DS09.tif 0301u4_DS10.tif 0301u4_DS11.tif 0301u4_DS12.tif 0301u4_DS13.tif 0301u4_DS14.tif 0301u4_DS15.tif 0301u4_DS16.tif 0301u4_DS17.tif 0301u4_DS18.tif 0301u4_DS19.tif 0301u4_DS20.tif 0301u4_DS21.tif 0301u4_DS22.tif 0301u4_DS23.tif 0301u4_DS24.tif |
|
Q:11/08/01 R:11/13/01 |
Plan Sheet / Specification Reference=Plantable
Geosynthetic Reinforced Wall
There is approximately 200,000 cy excavation and 300,000 backfill in these walls. Where is it paid for?
|
|
Q:11/08/01 R:11/20/01 R:12/28/01 |
Plan Sheet /
Specification Reference=BRIDGE 57-1028F
Where is the release of the existing tie-down paid at hinge?
|
|
Q:11/08/01 R:11/20/01 |
Plan Sheet /
Specification Reference=CIDH 600 mm, BRIDGE 57-0314
Sheet 1335 shows the pile rebar cages extending 4570 mm plus 50 mm above the bottom of footing elevation, but the footings are only 1220 mm in depth. Please clarify.
|
|
Q:11/08/01 R:11/13/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Plantable Geosynthetic Reinforced Wall
Note 14 on sheet 1440 shows the offset as 19.500 Rt. Sta. 21+67.00 "PGRLOL". Should this measurement be 9.500?
|
|
Q:11/08/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Vertical Drains
In the vertical drain specification on page 178, paragraph 2 requires that drains be extended 150 mm above the working surface. The third paragraph on the same page requires the vertical drains be extended 600 mm above the working surface. Please clarify.
|
|
Q:11/08/01 R:11/20/01 |
Plan Sheet /
Specification Reference=Stone Columns, Vertical Drains
Foundation treatment from PGRLOL Sta. 13+00 to 13+50 does not appear to be needed due to the bottom excavation existing below the approximate tip elevations shown in contours on sheet 1441. Please verify.
|
|
Q:11/08/01 R:11/26/01 |
Plan Sheet /
Specification Reference=CIDH
Please provide cross sections for the CIDH rebar between the construction joint and the tip of the permanent steel casing for all bridges with permanent casings.
|
|
Q:11/13/01 R:11/18/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Contract Plan Sheet#1389
The "specified pile tip elevations" given in the table indicate that all CIDH piles on this structure will be socketed into rock, yet no minimum "lengths of rock socket" are included in the table; can you please clarify your requirement here?
|
|
Q:11/13/01 R:11/15/01 |
Plan Sheet /
Specification Reference=Contract Plan Sheet #1060 and others
Permanent casing is shown as being required for the CIDH piles on several structures, yet nowhere is a minimum thickness specified; can you please indicate what these might be for each casing diameter?
|
|
Q:11/13/01 R:11/14/01 |
Plan Sheet /
Specification Reference=Contract Plan Sheet #1304
The 6 x 2 bundles of #32 bars shown on the Pile Elevation on sheet #1304 for the abutment piles at Los Penasquitos Channel bridge, will interfere with the proper placement of tremied concrete in the CIDH piles and will therefore, have to be plunged into the fresh concrete upon completion of the pour; can you please confirm that this will be acceptable?
|
|
Q:11/13/01 R:11/19/01 |
Plan Sheet /
Specification Reference=Bid Item 70, "Plantable Geosynthetic Reinforced
Wall," Plan sheet #1451, Specification section 10-1.39 of the Special Provisions.
The "Typical Cross Section" shown on plan sheet #1451 of the PGR Wall foundation details shows the 'actual temporary slope surface' on which the geocomposite drain is placed. On the cross sections, this slope is 1H:6V and has an excavated face over 20' tall. OSHA requires that a cut slope be no steeper than 1H:1V in type B soil. Has this material been analyzed and approved for the 1H:6V slope? If not, and the existing slope is excavated at a slope flatter than 1H:6V, where will this additional excavation and backfill be paid for, as structure excavation and backfill incidental to the PGR Wall or as roadway excavation under Bid Item 58?
|
|
Q:11/13/01 R:11/13/01 |
Plan Sheet /
Specification Reference=Bid Item 58, "Roadway Excavation"
Will the Earthwork Calculations performed from the cross sections be made available? These calculations serve as a good check to our own takeoff of the sections, and bring to light immediately any errors or discrepancies that might exist in the earthwork computations.
|
|
Q:11/14/01 R:11/19/01 R:11/26/01 R:01/11/02 |
Plan Sheet / Specification Reference=Bid
Items 222 & 225, Minor Concrete, Plan Sheets 539 & 222
The quantity summaries for minor concrete (Plan Sheet 539) indicate slope & median paving (Bid Item 222) to be measured by the cubic meter & textured concrete (Bid Item 225) to be measured by the square meter at the same locations. The only detail we can find for slope paving is on plan sheet 222, which shows pavers placed on a slurry subbase with concrete headers at top & bottom. Please clarify how you intend to measure and pay for slope paving and textured concrete. The following questions arise as a result of what is shown in the summaries: 1. Is all slope paving and textured concrete to be colored? |
|
Q:11/14/01 R:11/15/01 |
Plan Sheet / Specification Reference=Plan
Sheet 219, C-24
Does the "typical stepped slope detail" shown on C-24 applies to all slope? If not, what slope or slopes does this detail applies?
|
|
Q:11/14/01 R:11/19/01 R:12/28/01 |
Plan Sheet /
Reference= Bid Item 199, Plan Sheets 235 (D10) and 267 (42)
The plan view shows curvature in the 2275MM SSPP. There is no curve data given. If it is intended that the pipe be curved, is necessary to know the curve data to accurately detail and price the material.
|
|
Q:11/15/01 R:11/15/01 |
Plan Sheet / Reference= Section
19-1.36 EARTHWORK, SURCHARGE Sta. 14+00.000 to 15+00.000 & Sta. 19+72.000
to 20+58.000
Is the surcharge above the plantable wall to be placed before or after it's construction?
|
|
Q:11/15/01 R:11/19/01 |
Plan Sheet /
Reference= 3.4 M DIA. CIDH
Bent 5 of BR 57-1069F has a CIDH of diameter 3.4 M. There is no bid item for 3.4 M CIDH. Where will it be paid?
|
|
Q:11/15/01 R:11/26/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Item 58 roadway excavation
Existing contours on sheet D-22 do not match existing contours on sheet D-24. Please advise.
|
|
Q:11/15/01 R:11/15/01 |
Plan Sheet /
Specification Reference=Item 58 roadway excavation
Sheet D-16 shows new contours outside of the R/W. Is there work to be done outside of the R/W at this location?
|
|
Q:11/19/01 R:11/19/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Bid Items 99 & 102, Drawings Q-3/Q-9/Layout
drawings
The information shown on the quantity summary sheets for AC at misc areas (AC Gutters) does not match what is shown on the layout drawings or the typical sections. Also, the quantity of AC (Type A) does not appear to be correct for the areas of Misc AC paving indicated. Please clarify where AC gutters are to be placed.
|
|
Q:11/19/01 R:11/26/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Bid Items #183-187 are for Alternative Pipe Culvert.
Within the drainage details the specifics are written as to what is allowed as Alternative Pipe Culvert. Type S Corrugated Polyethylene is allowed but only with a max cover height of 3m. While I believe Caltrans old design manual only allowed for 3m the current manual allows for Corrugated Polyethylene to be installed up to 9m. Do you see any problem allowing Corrugated Polyethylene to be installed up to 9m (as per the sizes currently allowed by the Design Manual).
|
|
Q:11/20/01 R:12/28/01 |
Plan Sheet /
Specification Reference= Special Provisions Section 6
In Section 6 of the Special Provisions, Incentives and Disincentives for Completion of Work, paragraph 3 states that delays due to actions required by the Engineer performing normal inspection, testing and review duties will be included in the 900 working days allowed for completion of the designated portion of work. How many delay days should the Contractor estimate in his accelerated schedule for delays caused by the Engineer? In Section 10-1.14, Progress Schedule (Critical Path Method), State owned Float is defined as time saved on the critical path by actions of the State. After reading these two sections, it seems as though the Contractor is liable for the inaction of the engineer, yet the State is entitled to any time saved by the Engineer. Again, how is the Contractor to estimate delays caused by the Engineer that may prohibit the completion of the designated portion of work? Why is Caltrans entitled to any time saved on the critical path yet not liable for Engineer caused delays to the Contractors schedule?
|
|
Q:11/20/01 R:11/26/01 |
Plan Sheet / Specification Reference=Bid
Item 78: TEMPORARY EROSION CONTROL (TYPE 3), Bid Item 81: PURE LIVE SEED
(HYDROSEED 1)
The temporary erosion control bid items are confusing. On page WP-11 of the Plans, the area right of station 456+00 is to receive Temporary Erosion Control (Type 3) which contains seed and fertilizer. On page HP-2 the same area is to receive Hydro Seed 1 which contains seed and fertilizer. Is the Contractor required to remove the Temporary Erosion Control (Type 3) prior to applying Hydro Seed 1?
|
|
Q:11/20/01 R:11/26/01 |
Plan Sheet / Specification Reference=Section
10-1.53 CONCRETE PAVEMENT (WITH DOWELED TRANSVERSE WEAKENED PLANE JOINTS)
The second paragraph states that "Insert method for forming joints in pavement shall not be used". However, the Test Stripe section describes the use of mechanical inserters. What is the intent here?
|
|
Q:11/20/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Section 10-1.39 PLANTABLE GEOSYNTHETIC REINFORCED
WALL
Paragraph 2 - "Precast concrete elements to be colored per Section 72-6.03". Statement: Eliminating the integral color requirement could save money.
|
|
Q:11/20/01 R:12/28/01 |
Plan Sheet /
Specification Reference=BR # 57- 314 L/R, CARMEL MOUNTAIN ROAD, SPECIAL
PROVISIONS Page 99.
Required vehicle openings calls out two at 9.6 meters wide. Stage Drawings SC-78 & 79 show the following widths: Carmel Mountain Road EB 4.8M and WB 8.1M between k-rail. Please advise.
|
|
Q:11/20/01 R:12/28/01 |
Plan Sheet /
Specification Reference=BR # 57- 1069F S5, S805 Truck Connector, SPECIAL
PROVISIONS Page 99.
The Special Provisions only provide for a vehicle opening for Sorrento Valley Blvd. What are the vehicle openings for Route 5 SDR and SDL lines?
|
|
Q:11/20/01 R:12/28/01 |
Plan Sheet /
Specification Reference=BR # 57- 0513 L/R, Sorrento Valley Viaduct, SPECIAL
PROVISIONS Page 11.
Required vehicle openings calls for Roselle Street calls out 1 at 9.6 meters wide. Stage Drawings SC-48 & 49 shows one at 11.7 meters wide. Please advise.
|
|
Q:11/20/01 R:12/19/01 |
Plan Sheet / Specification Reference=BR
# 57- 0513 L/R, Sorrento Valley Viaduct, Drawing Sheet 1151/1549.
Elevations for the BB and EB stationing are not provided for the left side of the left bridge. Please advise.
|
|
Q:11/20/01 R:11/20/01 |
Plan Sheet / Specification Reference=
http://www.dot.ca.gov/dist11/construc/0301U4xsect.html
The following cross section files could not be downloaded from the server. FILES NOT FOUND. 0301U4 034.TIF
|
|
Q:11/25/01 R:12/28/01 R:01/07/02 |
Plan Sheet / Specification Reference=
Section 10-1.39 PLANTABLE GEOSYNTHETIC REINFORCED WALL
Special Provisions Section 10-1.39 page 161 EARTHWORK states that the fill material for the plantable geosynthetic reinforced earth wall shall meet gradation requirements as noted in the table on the same page. The table gives allowable percentages passing various sieve sizes and a plasticity index. The allowable percentages passing the #200 sieve and the maximum plasticity index of 20 indicate that a material, with strength properties well below the strength parameters that are normally used for the design of reinforced earth structures could be used. Based on our analysis the assumed soil strength would be 34 ° or better to make the existing design adequate. This strength may not be attainable given the guidelines for the material noted above.
|
|
Q:11/27/01 R:11/27/01 |
Plan Sheet / Specification Reference=Item
150, PTFE Spherical Bearing, Sheets No. 1081 of 1549 & 1404 of 1549,
Section No. 10-1.59
It is noted on Page 219 of the Contract Special Provisions that a penalty is actually assessed to manufacturers of PTFE Spherical Bearings who are not located in California. The $5,000 or $15,000 amount that can be reduced to the contractor becomes a large factor in the total costs and therefore gives the advantage to only manufacturers in California. To the best of our knowledge there is only one company in California that is approved to supply PTFE Spherical Bearing Assemblies. We are quite certain that it is not Caltrans intent to have a sole source. Please clarify.
|
|
Q:11/28/01 R:11/28/01 |
Plan Sheet / Specification Reference=Bid
Items 58, 63, and 64; Roadway Excavation and Retaining Walls Structure
Excavation and Backfill. Cross section sheets 220-223 and 333-336.
Newly issued cross section sheets 220-223 and 333-336 (STA "NB" 527+26.457 to 528+40 rightside) show the 470 retaining wall as original ground (already built), yet the construction of this wall is included in the plans. Please clarify.
|
|
Q:12/05/01 R:01/07/02 R:01/15/02 |
Plan Sheet / Specification Reference=Minor
Concrete (Misc Construction), Plan Sheet 539 of 1549, Bid Item 222, Bid
Item 219
The quantities sheet 539 shows 818 m3 PCC slope paving. It appears that this quantity is paid under Bid Item 222 "Minor Concrete (misc. Construction)" and not under Bid Item 219 "Slope Paving (Concrete). Please clarify, as Bid Item 219 is a Final Pay Item.
|
|
Q:12/05/01 R:12/11/01 R:01/07/02 |
Plan Sheet / Specification Reference=Bid
Item 58, "Roadway Excavation," and page 4 of the Materials Information
Brochure, Book 1 of 2.
Please elaborate on the requirements for disposing of excess material at the site between Del Mar Heights Road and Villa de La Valle (i.e. site preparation, compaction, erosion and drainage control, SWPPP, and traffic control). Is this an engineered fill with designed limits and slopes, or simply a dump site requiring knockdown of loads only?
|
|
Q:11/12/01 R:12/17/01 |
Plan Sheet /
Specification Reference=70 Plantable geo retaining wall
How will the plantable geo wall be measured for payment? The spec is unclear as to whether the wall will be measured from bottom of "bottom header" to the top of the "top header," or from finish grade (no burial) at face of wall to top of wall?
|
|
Q:12/06/01 R:12/17/01 |
Plan Sheet /
Specification Reference=Bridge No. 57-1069F, S5-S805 Truck Connector
On plan sheet 1061, the chart of Isolation Casing Location & Length of Payment does not list bents 13 or 14. At bent 13, the difference between finish grade and pile cutoff elevation is 3.45m. At bent 14, the difference is 9.73m. At all other bent locations, the isolation casing length is equal to the distance from pile cutoff to finish grade. Is the intent not to install isolation casings at bents 13 and 14?
|
|
Q:12/11/01 R:12/17/01 |
Plan Sheet / Specification Reference=Section
13-1.02 RAILROAD REQUIREMENTS
On page 369 of the Special Provisions, the first sentence of the fifth paragraph reads "The Contractors falsework....shall be supported from the bridge superstructure." Can we use falsework in the railroad right of way, supported on ground surface, as long as there is no encroachment of the designated temporary clearances, as stated in the subsequent Special provisions sentences?
|
|
Q:12/11/01 R:12/28/01 |
Plan Sheet / Specification Reference=
As of this date we are not aware that
addendum No 2 has been issued, and there are still many inquiries which
have not been answered or are still pending. In order to complete
a responsive bid, it is
|
|
Q:12/14/01 R:01/11/02 |
Plan Sheet / Specification Reference=22658
- STUCCO ARCH TEXTURE
Retaining Wall 6 (Sheet 667 of 1549), Retaining Wall 543A (Sheet 688 of 1549), Retaining Wall 545B (Sheet 698 of 1549) The referenced plans show a "STUCCO"
Architectural Treatment which is 73 mm thick.
If the 73 mm is the correct thickness, what material is required for the additional 54 mm of thickness? |
|
Q:12/13/01 R:01/08/02 R:01/15/02 |
Plan Sheet / Specification Reference=Item
#72(S), SOIL CEMENT, Special provisions Section 10-1.41, Page 174
The unit weight of soil cement samples is specified to be at least 21kN/m3, which exceeds the typical value for mixed-in-place soil cement by -6kN/m3. The specified weight therefore is unachievable. Will a Unit Weight in the range of 15kN/m3 be acceptable, as long as the strength requirements for the soil cement are met?
|
|
Q:12/13/01 R:01/04/02 |
Plan Sheet / Specification Reference=Item
#71(S) STONE COLUMN (1.1M), Section 10-1.40
The minimum column diameter at any depth is required to be at least 1.1M, and is expected to be increased "if necessary." This large of a diameter at every depth, regardless of soil type or condition, is generally unachievable with the specified equipment or any conventional vibrators. Even larger diameters would be even less achievable. Is an average of 1.1M desired, instead of a minimum of 1.1M?
"The diameter...shall be no less than 1.1 m and shall be increased..." The minimum area replacement ratio shall be 0.19. The bidder may submit a Cost Reduction Incentive in conformance with contract special provision section 5-1.019 "Cost Reduction Incentive", page 26, to reduce the stone column diameter and revise stone column layout. |
|
Q:12/13/01 R:01/08/02 |
Plan Sheet / Specification Reference=Item
#71(S) STONE COLUMN (1.1M), Section 10-1.40, Page 164
The stone column in-fill is specified to be well-graded, and conform to the grading limits published on page 164. Such well-graded aggregate is necessary for mixing concrete, but causes plugging and diameter-achievement problems if used to construct stone columns. Gap-graded stone 3/4" to 1" in size is used when economy and maximum column diameter are desired. As long as all other stone criteria are met, will crushed 3/4" to 1" stone acceptable?
|
|
Q:12/13/01 R:01/08/02 R:01/15/02 |
Plan Sheet / Specification Reference=Item
#71(S) STONE COLUMN (1.1M), Section 10-1.40, Page 167
All soils with an Ic less than 2.95 are specified to be included in the calculation of average corrected cone tip resistance, with minimum and average values of 8 MPa and 10.5 MPa being required, respectively. Such design tip resistance values typically apply only to soils with Ic's in the range of 2.4 to 2.6, because soils with Ic values higher than -2.6 are relatively unaffected by stone column construction. Is this value of Ic=2.95 subject to review?
|
|
Q:12/13/01 R:12/21/01 |
Plan Sheet / Specification Reference=Item
Nos. 71 (S), 72(S); STONE COLUMN, SOIL CEMENT, PREFABRICATED VERTICAL DRAIN,
Special Provisions Sections 10-1.40 through 1.42
Phase 1 includes two limited areas of stone columns to be constructed west of I-5, with the remainder of Stone Columns to be constructed during Phase 2. Do the production requirements for the Order of Work for soil cement and prefabricated vertical drains also apply to these initial areas of stone columns?
|
|
Q:12/14/01 R:12/18/01 |
Plan Sheet / Specification Reference=Item
70 Plantable Geosynthetic Reinforced Wall, Varies, 10-1.39
When can we anticipate a response from the State on the items pertaining to the wall facing? As a supplier we need to be getting scopes of work out to the contractors this week. We cannot do this without some direction on whether or not we can legally supply the precast concrete facing. The Holidays are fast approaching. These questions have been outstanding for more than a month!
|
|
Q:12/14/01 R:01/10/02 |
Plan Sheet / Specification Reference=Item
14 CONSTRUCTION AREA SIGNS, Contract drawings SC-1 thru SC-107 and CS-1
thru CS-10, Special provisions Section 10-1.20
The Engineers quantity for construction area signs calcs for a total of 390 signs. Our quantity comes to a total of 593 signs. Please verify that the Engineers quantity is correct.
|
|
Q:12/18/01 R:01/04/02 R:01/15/02 |
Plan Sheet / Specification Reference=Item
# 71(S), STONE COLUMNS, Special Provisions Section 10-1.40, page
165
The vibrating probes are required to be"...rated by the manufacturer to provide at least ...25 metric ton of horizontal force...' A maximum required rating of 20 tons is typical for the vibrators employed on work of this nature on Caltrans projects. Will a maximum manufacturer's rating of 20 metric tons be acceptable for this project?
|
|
Q:12/18/01 R:12/28/01 |
Plan Sheet /
Specification Reference=Item # 73(S), PREFABRICATED VERTICAL DRAIN",
Special Provisions Section 10-1.42, page 178
Paragraphs 11 and 12 of this section specify two different minimum lengths of prefabricated vertical drain to "...(extend) above the working surface....", those being 150 mm and 600 mm. Please clarify.
|
|
Q:12/18/01 R:12/28/01 |
Plan Sheet / Specification Reference=
Section 10-1.01 "ORDER OF WORK," Paragraph 8; and Section 10-1.42, "PREFABRICATED
VERTICAL DRAIN", page 178
The "order of work" requires the soil cement mixing and the prefabricated vertical drains to be installed prior to construction of any stone columns in an area, and prefabricated vertical drains are required to extend above the working surface. However, construction of stone columns will disrupt ( and not densify) the upper 2-4 feet of soil at the working surface, requiring surface recompaction. This seems to conflict with the above-ground drain requirement. Please clarify.
|
|
Q:12/18/01 R:01/08/02 R:01/15/02 |
Plan Sheet / Specification Reference=
"SOIL CEMENT", Special provisions Section 10-1.41, "WetGrab Soil-Cement
Samples", Paragraph 3.
Each soil-cement sample is required to be at least 1.1 cubic feet in volume, to fill a minimum of (6) cylinders 150 mm diameter by 300 mm. This is a very large sampler volume to try and extend to any significant depth in a soil-cement column. Will typical cylinder sizes of 75 mm diameter by 150 mm be acceptable for each sample retrieval and test?
|
|
Q:12/18/01 R:12/26/01 |
Plan Sheet / Specification Reference=Item
70 Plantable Geosynthetic Reinforced Wall,1451,1452, 1453, 1454,
10-39.1
Subdrain detail sheet 1451 indicates the drainage system is to run from sta. 9+40 to 21+67. Indicates further that geocomposite is to extend 2/3 height of the wall. Sections on sheets 1452, 1453 and 1454 indicate that the geocomposite is to be attached to the "actual excavated temporary slope surface..." The section shows it thus. Most of the wall is constructed in back cuts considerably less than 2/3 wall height. What governs, cut height or 2/3 wall height?
|
|
Q:12/19/01 R:12/28/01 |
Plan Sheet / Specification Reference=Item
107
Item summary 107 referencing DRIVE STEEL PILE (HP 305 x 110) states 500 EA., takeoff shows 498 Ea. Please advise of correct quantity.
|
|
Q:12/24/01 R:01/15/02 |
Plan Sheet / Specification Reference=150,
PTFE SPHERICAL BEARING,SHEET NO.
1081 OF 1549 & 1404 OF 1549,SECTION NO. 10-1.59 FURTHER TO PREVIOUSLY POSTED REPLY TO QUESTION 56, YOUR REPLY IS AMBIGUOUS, THE QUESTIONS POSED HAS NOT BEEN ANSWERED. THERE ARE ONLY A FEW MANUFACTURERS OF PTFE SPHERICAL BEARINGS, REGARDLESS OF THE TYPE, IN THE UNITED STATES AND ONLY ONE IN CALIFORNIA. THE ASSESSMENT OF $5000 OR $15000 TO MANUFACTURERS OUTSIDE OF CALIFORNIA GIVES A DISTINCT ADVANTAGE TO THE ONLY SOURCE IN CALIFORNIA. PLEASE ANSWER.
|
|
Q:12/26/01 R:01/04/02 |
Plan Sheet / Specification Reference=Item
# 70 (S): STONE COLUMN, Special provisions 10-1.40, "Verification Testing,"
pages 166-167
In paragraph 2, a comparing set of two before and after CPTs is required for every 144 square meters of stone column area. In paragraph 3, CPT's are again mentioned, to be performed for each 288 square meters "at random locations identified by the Engineer during construction...." This implies that an average of 2.5 cone penetration tests will be performed at every 144 square meters of stone column area. Is this a correct interpretation?
|
|
Q:12/26/01 R:01/08/02 |
Plan Sheet / Specification Reference=
Item # 71 (S): SOIL-CEMENT, Special provisions Section 10-1.41, "Wet Grab
Soil- Cement Samples, " page 172
The frequency and number of required Wet Grab Soil Cement Samples would result in significantly lower average production rates of soil-cement elements, with questionable benefits to the overall QC of the project. Given that systematic procedures and equipment for this installation method will be verified by initial test programs and geotechnical conditions are not expected to vary widely over very short distances, can testing frequency be lowered?
|
|
Q:12/26/01 R:01/08/02 |
Plan Sheet / Specification Reference=
Item # 71 (S): SOIL-CEMENT, Special provisions Section 10-1.41, "DEEP MIXING,"
page 169
The average 56-average unconfined compressive strength of soil cement throughout the depth of each soil-cement element is specified to be no less than 2,000 kPa. Given the fine grained nature of much of the soil described on the geotechnical boring logs, a more realistic strength value for a constructable soil-cement element would be in the range of 690-700 kPa. Is this higher-than-typical 2,000 kPa strength value subject to review?
|
|
Q:12/26/01 R:01/09/02 |
Plan Sheet / Specification Reference=
Item # 71 (S): SOIL-CEMENT, Special provisions Section 10-1.41, "Wet Grab
Soil- Cement Samples, " page 172
The depths of retrieval for non-cured soil-cement samples are to be "selected by the Engineer," with no maximum sampling depth specified. The practical maximum depth for such wet-grab samples is approximately 40 feet. If the Engineer foresees a requirement for retrieval of wet-grab samples from greater depths than 40 feet, this requirement will be problematic for the Specialty Contractor. Will a depth limit of 40 feet be acceptable for wet sampling?
|
|
Q:12/26/01 R:01/18/02
|
Plan Sheet / Specification Reference=
Item # 71 (S): SOIL-CEMENT, Special provisions Section 10-1.41, "CONSTRUCTION,
" page 172
Deep Soil Mixing is a relatively new technique; as such, some very competent individuals might not meet some of the experience longevity requirements in this specific technique, especially for the depths anticipated. Specifically, few high-quality Project Engineers can show "five full years experience... in deep soil-cement mixing." Will a resume of individuals with sound experience in Ground Modification -- including Soil-Cement Mixing be considered?
|
|
Q:01/02/02 R:01/07/02 R:01/18/02 |
Plan Sheet / Specification Reference=
Contract Item: 251, Standard Plan A76A and Contract Plan Sheets.
Details, including reinforcing steel for roadway offsets in excess of 305 mm, the construction of Type 60C Barrier is affected by the pavement offsets. Please provide this information as it appears to be missing from Contract Plans. These offsets cannot be calculated due to most 60C Barrier construction on pavement which matches existing roadway elevations. |
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #22, Plan Sheets 540, 620, 648 and 658. Does upper pedestal (above link beam and between the 60E barrier) pay as part of Contract Item 139?
|
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #22 and RSP S40U. Type J post requires 920mm x 5.2m pile depth. Please confirm that the left post CIDH is to be 9.0m (29'-6 1/2") long.
|
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #16. RSP S40U calls for pile length of 6.7m. Confirm that both left and right side CIDH requires pile depth of 9.7m (31'-0").
|
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #20. RSP S40U calls for pile length of 5.2m. Confirm that both left and right side CIDH requires pile depth of 9.0m (29'-6 1/2").
|
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #21. RSP S40U calls for pile length of 6.7m. With 1.0m extended length of 60E barrier, these would be 7.7m CIDH pile lengths. Confirm that both left and right side CIDH requires pile depth of 10.2m (33'-5").
|
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #23. RSP S40U requires 5.2m for Type J post. Confirm that left and right legs for Type J post are to be 7.0m (23'-0") and 8.0M (26'-7") pile depths.
|
|
Q:01/02/02 R:01/16/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #24. RSP S40U only requires 6.7m for Type T post. Confirm that CIDH is to be 10.2m (33'-5").
|
|
Q:01/02/02 R:01/16/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #26 and #29. RSP S20B calls for 914mm x 4.0m CIDH for post Type 10NPS. Clarify the required size shown as 760mm x 4.6m.
|
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #30. Confirm right and left legs for Type J post are 9.0m (29'-0") and 8.0m (26'-3") pile depths. RSP S40U only requires 5.2m for Type J post.
|
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #34, 35 and 37. Confirm that CIDH is to be 9.7m (31'0"). RSP S40U only requires 6.7m for Type T post.
|
|
Q:01/02/02 R:01/15/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #36, left and right legs. Confirm that CIDH are to be 11.8m (38'-9") and 11.2m (36'-9"). RSP S40U only requires 5.2m for Type J post.
|
|
Q:01/02/02 R:01/11/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #39. Confirm that CIDH are to be 10.2m (33'-5") and 9.7m (31'-10"). RSP S40U only requires 6.7m for Type S post.
|
|
Q:01/02/02 R:01/16/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #42. Per detail shown on Plan Sheet 634, sign mounts to Retaining Wall #569, yet the table on Sheet 649 provides for a 1070mm x 6.7m CIDH foundation. Please clarify.
|
|
Q:01/02/02 R:01/16/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #45 and 46. Clarify the CIDH as shown is 760mm x 5.5m and 760mm x 8.5m. RSP S20B calls for 916mm x 4.6 CIDH for 12NPS sign post.
|
|
Q:01/02/02 R:01/16/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #47. Clarify the CIDH as shown is 920mm x 4.9m. RSP S13 requires 760mm x 4.5 CIDH for post Type II.
|
|
Q:01/02/02 R:01/16/02 |
Plan Sheet / Specification Reference=
Items 174, 175 and 176, Plan Sheets 548 to 666.
Reference Sign #52. Clarify the CIDH as shown is 760mm x 4.6. RSP S20B requires 914mm x 4.6 for post Type 12NPS.
|
|
Q:01/02/02 R:01/04/02 |
Plan Sheet / Specification Reference=
Addendum 2 - page 7
Under the paragraph for payment of longitudinal isolation joint it implies that the payment for the isolation joint will be a separate pay item however the revised bid schedule does not include that pay item. How is it to be paid for?
|
|
Q:01/03/02 R:01/15/02 |
Plan Sheet / Specification Reference=Sheet
no. 1041 of 1549, Foundation Plan No.5, BR# 57-1069F, S5-S805 Truck Connector.
There appears to be a conflict between the new bridge and the high voltage cables shown on this plan. The finish elevation of the new bridge deck at the intersection with the cables is approximately elevation 30.30m. Power Pole C (PP#96273) has three (3) cables at elevation 33.64m and two (2) cables at elevation 27.58m. These cables are not referenced in Obstructions of the Special Provisions. If these cables are in conflict, please provide the relocation schedule and new cable elevations and horizontal locations.
|
|
Q:01/03/02 R:01/15/02 |
Plan Sheet / Specification Reference=Bid
Item No. 158
The Engineers Estimate shows 12 m but the plans show 24 m. Please clarify.
|
|
Q:01/03/02 R:01/23/02 |
Plan Sheet / Specification Reference=
Please specify the criteria of foundation treatment (overexcavation) on retaining walls 543B & 545C shown on sheet 721.
B) Retaining wall 545C, What control
the overexcavation ?
2.Starting from the point where the existing ground intersect the proposed grade projected horizontally to a point where it intersect the imaginary 1:1.75 line, then projected at 1:1 temporary cut slope to daylite line. 3. Is there a maximum depth of overexcavation
since some portion of the said wall is found in cut area?
|
|
Q:01/03/02 R:01/07/02 |
Plan Sheet / Specification Reference=
Item 70 Plantable Geosynthetic Reinforced Wall
On which item will the foundation treatment on the PGR walls be paid?
|
|
Q:01/04/02 R:01/11/02 |
Plan Sheet / Specification Reference=Bridge
No. 57-1069F over Sorrento Valley Blvd. (Addendum No.2 dated 12/28/2001),
Section 10-1.21, Maintaining Traffic.
The traffic opening was changed from two (2) 7.7m vehicular openings (with ped opening in the median) to a single 19.5m opening (with ped opening in the median). Please clarify ped opening location.
|
|
Q:01/04/02 R:01/15/02 |
Plan Sheet / Specification Reference=Bridge
No. 57-1070G over Sorrento Valley Blvd. (Addendum No.2 dated 12/28/2001),
Section 10-1.21, Maintaining Traffic.
The traffic opening was changed from two (2) 7.7m vehicular openings (with ped opening in the median) to a single 19.5m opening (with ped opening in the median). Please clarify ped opening location.
|
|
Q:01/04/02 R:01/07/02 R:01/11/02 R:01/15/02 |
Plan Sheet / Specification Reference=(Addendum
No.2 dated 12/28/2001)
There are three (3) runs of Type 60 Barrier that are duplicated on Summary of Quantities, Sheet Q-4 (plan Sheet 541). The duplication is from Station 547+70 to Station 553+48 (578m), Station 553+73 to Station 553+93 (20m), and Station 554+18 to Station 557+84 (368m). The barrier from Station 526+72 (56m) is Type 60A Barrier and included in the 60A quantities (plan Sheet 1298). The Type 60 barrier from Station 542+35 to Station 549+54 includes 81m of Type 60A and is included in the 60A bid item (see Plan Sheet 1326). Total of the above is 1,103m under the bid quantity shown in Addendum No. 2 (Bid Item 249 at 6,500m). Please clarify.
|
|
Q:01/04/02 R:01/15/02 |
Plan Sheet / Specification Reference=Addendum
#2 Quantity Summaries/Plan Revisions
According to quantity summary sheet Q-2, the quantity for Minor Concrete (Misc Construction) includes PCC median paving (53.43 M3) and PCC slope paving (818.18 M3) measured by the cubic meter. The same summary sheet shows paving at the same locations listed as Minor Concrete (Textured Paving) measured by the square meter. Is the median paving and slope paving to be measured and paid for as bid item 222 or item 225?
|
|
Q:01/04/02 R:01/11/02 |
Plan Sheet / Specification Reference=Addendum
#2 Quantity Summaries/Plan Revisions
The change of quantities for bid items 97 - 104 do not appear to match the changes shown on quantity summary sheet Q-1 (sheet 538). For example, the PCCP quantity has decreased by a minor amount in the summary, yet the bid quantity has increased. Please clarify.
|
|
Q:01/04/02 R:01/11/02 |
Plan Sheet / Specification Reference=Addendum
#2 Quantity Summaries/Plan Revisions
Addendum #2 directed the contractor to change the call out for "Relocate Water Meter" to "Water Meter (Building)" on plan sheet 418. If the water meter is to be included in bid item 288, should item 41 be deleted?
|
|
Q:01/04/02 R:01/06/02 R:01/11/02 |
Plan Sheet / Specification Reference=Addendum
#2 Quantity Summaries/Plan Revisions
With reference to inquiry #13, it would appear that the typical cross sections shown on sheets X-5 & X-6 are still in conflict with those shown on sheet X-15. Is it correct to assume that the information shown on sheet X-15 is the intended paving section?
|
|
Q:01/04/02 R:01/05/02 |
Plan Sheet / Specification Reference=Addendum
#2 Quantity Summaries/Plan Revisions
Addendum #2 (Page 10) indicated that additional Material Information was to be attached. We did not receive that information. When will the referenced information be available?
G2 W1 F1 F1A F14 F19 |
|
Q:01/04/02 R:01/15/02 |
Plan Sheet / Specification Reference=Item
72: Soil Cement
Payment for Soil Cement is contract price per cubic meter for soil-cement. In the measurement clause above the Payment clause - it states "The quantity of soil-cement to be paid for shall be the QUANTITY OF CEMENT FURNISHED to be mixed with the insitu soil within the soil-cement area. Please clarify the volume is not quantity of cement to be furnished for the mixing and the payment quantity shall be the complete treated volume mass of soil-cement.
|
|
Q:01/04/02 R:01/07/02 |
Plan Sheet / Specification Reference=Item
72: Soil Cement
The specification stipulates installation
of soil cement by deep mixing auger method.
|
|
Q:01/07/02 R:01/07/02 R:01/11/02 |
Plan Sheet / Specification Reference=Section
10-1.32 TEMPORARY CRASH CUSHION (ADIEM), Section 10-1.98 CRASH CUSHION
(ADIEM)
The telephone number listed in both sections is incorrect, please provide a correct contact number.
|
|
Q:01/08/02 R:01/11/02 R:01/15/02 |
Plan Sheet / Specification Reference=Slope
Paving quantities/details
According to the bridge plans, the only
location that receives slope paving is at abutment 1 on the N805-N5 truck
connector. The quantity given on the bridge plans is 12 M3, which
agrees with bid item
|
|
Q:01/09/02 R:01/11/02 |
Plan Sheet / Specification Reference=Special
provisions Section 10-1.39 "Plantable Geosynthetic Reinforced Wall"
Addendum No. 2 revised the gradation and property requirements for the wall fill material to that usually specified for MSE backfill material. The addendum also deleted the first sentence , "Fill material for plantable geosynthetic reinforced wall shall consist of material excavated from within the project limits." In the Bidder's Inquiries, the response to question No. 55 states that the backfill material as revised per Addenda No. 2 should be obtainable from within the project excavation limits located East of I-5 between Station 529 to Station 549+00 "NB" and West of I-5 between Station 544+50 to Station 550+00 "SB". Who is responsibility for supplying backfill material if the excavation within the limits listed does meet the Addenda No. 2 backfill specifications, the Contractor or Caltrans?
|
|
Q:01/09/02 R:01/11/02 |
Plan Sheet / Specification Reference=Sheet
Nos. 1030,1111,1183,1184,1231,1302 Pile Data Tables
In the event that the rock level is different from that assumed in the documents, will a) the "specified pile tip elevation" be adhered to, or, b) will the "intended length of rock socket" govern?
a) No. b) Yes. |
|
Q:01/09/02 R:01/11/02 |
Plan Sheet / Specification Reference=Sheet#
1030, Index to Plans, Pile Data Table, Notes
Does the note defining the casing tip
as being 600mm below the top of rock
"....If the permanent steel casing is not installed into bedrock at the permanent steel casing tip elevation indicated in the pile data table shown on the plans, the Contractor shall extend the cast-in-drilled hole concrete piling...to achieve the required embedment into bedrock...." a) Yes. b) See Section 5-1.04 "Coordination and Interpretation of Plans, Standard Specifications, and Special Provisions": "....special provisions shall govern over....the plans." |
|
Q:01/10/02 R:01/15/02 |
Plan Sheet / Specification Reference=Addenda
No. 2 Section 5-1.18 AREAS FOR THE CONTRACTOR'S USE, Plan sheet L-38
The area shown on plan sheet L-38 shows partial use of the entire parcel. Can we request use of the additional area? Is a permit necessary?
L-38 |
|
Q:01/14/02 R:01/14/02 |
Plan Sheet / Specification Reference=
Plan Sheet 960, 963, 964 & 965 Regarding Changeable Message Sign System
Per the notes: Note 1 CMS Model 500 shall be State furnished ...., but if you look at these sheets it is requiring 78C, CMSH#4, CMSH#5. Are the harnesses listed in Delta 4, CMSH#4 & CMSH#5 on the sheets above to be furnished by the State with the State furnished CMS Model 500 signs or are we to include the harnesses as part of the quote at bid time?
|
|
Q:01/15/02 R:01/16/02 |
Plan Sheet / Specification Reference=
The material specs for the Permanent Steel Casings are not specific enough to determine whether they are ASTM A252 Grade 2 or ASTM A252 Grade 3. Please advise.
Since permanent casings shown on the contract documenets are greater than 360 mm in diameter, they shall conform to ASTM Designation: A252, Grade 3. |
|
Q:01/15/02 R:01/18/02 |
Plan Sheet / Specification Reference=Br.
No. 57-0512R
Please advise maximum allowable overhang at each end of the 2.0 & 1.7 bulb-tee girders, according to the design.
|
|
Q:01/16/02 R:01/23/02 |
Plan Sheet / Specification Reference=Item
# 73 (S), PREFABRICATED VERTICAL DRAINS, Special Provisions Section 10-1.42,
Addendum No. 2.
The revised criteria for installing the drains include a warning for the installation device to not damage the filter fabric, and later warning for any shallow pre-drilling to not significantly impact the fabric and permeable material. Both of these statements imply that the drainage blanket would be constructed prior to the installation of prefabricated vertical drains. Since the drains must be installed prior to construction of the Stone Columns, this construction sequence would result in severe damage to the drainage blanket by the vibrator, and would result in clogging of the permeable blanket material with fine-grained spoils from the installation process. Please clarify that the drainage blanket must be constructed after the Stone-Column construction.
"Construction of stone columns shall not begin until after the installation of prefabricated vertical drains...." Since the drainage blanket is included in the stone column work, (see sheet 1452 and 1453 of 1549, Foundation Details No. 2 and Foundation Details No. 3, respectively) the drainage blanket is to be placed as shown on the plans. |
|
Q:01/16/02 R:01/16/02 |
Plan Sheet / Specification Reference=Item
# 72, SOIL CEMENT, Special Provisions Section 10-1.41
It is unclear who is to pay for the UCS and cement content tests on Wet-Grab and Core Samples. Pg. 71 says "...The Engineer will form, cure, transport, and test the samples and report the test results..." Pg. 172 says "...the Contractor shall test...for unconfined compressive strength..." and submit results to the Engineer. Pg. 173 calls for core samples to be submitted to the Engineer "...for subsequent evaluation and testing..." And Pg. 175, under "PAYMENT," states that full compensation for soil-cement quality control shall be included in the contract price paid to the contractor. Please clarify who is to pay for which tests, and whether any specific laboratory has to be used. |
|
Q:01/16/02 R:01/16/02 |
Plan Sheet / Specification Reference=Website
Inquiry Numbers 91, 92, 97, 99 and 100
Request clarification to Department's responses and confirmation that "change" to handle incorrect CIDH sign foundation will be per Section 4-1.03C, not as per 4-1.03B(1) or 4-1.03B(2). Adjustment methods of 4-1.03B(1) and (2) will be inappropriate, due to the many corrections and the unusual lengths of these foundations and other CIDH foundations noted on pre-bid inquiries.
|
|
Q:01/16/02 R:01/23/02 |
Plan Sheet / Specification Reference=Item
No. 81: PURE LIVE SEED (HYDROSEED) and Item No. 84: PURE LIVE SEED (SEEDING)
There is no seed mix in the specifications. Please supply the seed mix to bid on these items?
|
|
Q:01/17/02 R:01/22/02 |
Plan Sheet / Specification Reference=Item
# 72 (S), Soil Cement
The requirement for 2,000kPa average UCS strength for soil-cement elements in many of the clayey zones --- due to their plasticity -- will not be able to be achieved with conventional mixing operations. Will it be acceptable to treat an area greater than the minimum 50% of the designated zone, in order for soil- cement of a lower strength to accomplish the same purpose?
|
|
Q:01/18/02 R:01/18/02 |
Plan Sheet / Specification Reference=Sec.
10-1.53 Concrete Pavement (with doweled transverse weakened plane joints).
When paving against the existing PCCP, will you require a profile grind on the existing PCCP?
|
|
Q:01/18/02 R:01/18/02 |
Plan Sheet / Specification Reference=Plan
Sheet No. 1281 of 1549
Reference: "Girder Elevation". Dimension line titled "% Debonded strands" Please verify that 70% of the total prestress strands are debonded for a distance of "L2". Or, is only 30% debonded for a distance of "L2"?
|
|
Q:01/18/02 R:01/23/02 |
Plan Sheet / Specification Reference=Plan
Sheet No. 1281 of 1549
Reference: "Girder Elevation". Dimension line titled "% Debonded strands" Please provide a dimension for "L2"
|
|
Q:01/18/02 R:01/23/02 |
Plan Sheet / Specification Reference=Section
10-2 Highway Planting & Irrigation Systems.
Plan sheets 817 (HP-30) refer to seed type 1 (Legend lists seed # 6 at (biorestoration)). Plan sheets 823-826 (HP-36 to HP-39) refer to seed type 2 (seeding on plantable geo-grid retaining (PGR) wall. Need to know the seed composition and type of application required at these areas.
|
|
Q:01/18/02 R:01/22/02 |
Plan Sheet / Specification Reference=Bid
Item: 71(S) Stone Column
Achieving a minimum stone column of
1.1M diameter by dry bottom feed vibro displacement methods is highly unlikely.
Would vibro displacement of stone placed in a 1.1M drilled hole be considered
equivalent?
|
|
Q:01/21/02 R:01/22/02 |
Plan Sheet / Specification Reference=Item
# 72 (S), Soil Cement
The re-confirmed requirement to achieve 1,800 kPa and 2,000 kPa average UCS strengths at all depths of soil-cement elements is unlikely, due to the zones of plastic clays at various -- and typically deeper -- depths. Is this full- depth requirement due to high design surcharge loads that will be imposed at the tops of the elements, by the toe of the new PGR wall? If so, is there a depth at which the 2,000 kPa requirement can be lessened, due to dissipation of the wall loads with depth? Most of the shallower soils are sandy in nature, and only a minor amount of overdrilling and replacement of shallow soils with granular soils all the UCS strength requirement to be achieved to some prespecified depth...but NOT to the full depth of all soil-cement elements.
|
|
Q:01/22/02 R:01/23/02 |
Plan Sheet / Specification Reference=PTFE
Spherical Bearing, Sheet No. 1081 of 1549 & 1404 of 1549, Section No.
10-1.59
In respect to question 78 & question 56, once again your reply is ambiguous and the question has not been answered. The assessment of $5,000 or $15,000 for shop inspection expenses by the State clearly gives the distinct advantage to the only source in California. We do not disagree that there are expenses involved, however, in all fairness should not the expense be the same to all regardless of their location. Please answer.
|
|
Q:01/22/02 R:01/23/02 |
Plan Sheet / Specification Reference=Bid
Item 70, Plantable Geosynthetic Reinforced Wall.
Is the topsoil placed on the wall face incidental to the PGR wall or is it paid under Bid Item 75? Can this topsoil be obtained from within the project limits or does it have to be imported?
|
|
Q:01/23/02 R:01/23/02 |
Plan Sheet / Specification Reference=PLANHOLDERS
LIST
The planholders list does not provide telephone or fax numbers , how can we obtain these?
|
|
Q:01/23/02 R:01/23/02 |
Plan Sheet / Specification Reference=Section
10-1.86 Misc Conc Const
The specs state that samples of the textured paving are available for review, where and when can we view these?
|
|
Q:01/23/02 R:01/23/02 |
Plan Sheet / Specification Reference=Section
10-3.16 PULL BOXES
Have not been able to locate specs for Caltrans pull box. Are you going with armorcast or concrete? And do you have a spec number?
|
|
Q:01/23/02 R:01/23/02 |
Plan Sheet / Specification Reference=Section
10-1.39 PLANTABLE GEOSYNTHETIC REINFORCED WALL
For the PRECAST CONCRETE WALL FACE as stated on sheet 161 what is the Color No. 23531 of the Federal Standard 595B?
|